# SR 597 (Dale Mabry Highway) Repaving from South Avenue to Waters Avenue 447973-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Construction |
| Limits | South Avenue to Waters Avenue |
| Project Start | Early 2027 |
| Length | 3.168 Miles |
| City | Tampa |
| County | Hillsborough |
| Road | Dale Mabry Highway SR 597 |
| Construction Cost | $7.4 million |
| Estimated Completion | Fall 2027 |
| Contractor | Hubbard Construction Company |
| Contact Information |
| Project Information |
| Maricelle Venegas | 813-975-6204 |
| Maricelle.Venegas@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
## About
This project will repave SR 597 (Dale Mabry Highway) between South Avenue and Waters Avenue in Tampa, Hillsborough County.