# Morris Bridge Road Repaving from Davis Road to Fletcher Avenue 439532-1-52-01
| Project Details |
| Work Type | Repaving |
| Phase | Completed |
| Limits | from Davis Road to Fletcher Avenue |
| Project Start | March 2021 |
| Length | 2.2 miles |
| City | Temple Terrace |
| County | Hillsborough |
| Construction Cost | $4.5 million |
| Estimated Completion | Late 2022 |
| Contractor | Ranger Construction Industries, Inc. |
Contact Information
Project Information
Andrew Williams
813-612-3200
Andrew.Williams@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
Map data ©2022
## About
As of Monday, October 31, 2022, all construction activities associated with this project have been completed.
This project repaved Morris Bridge Road between Davis Road and Fletcher Avenue in Temple Terrace.
Other improvements:
• added a six-foot sidewalk along the west side of the road between Davis Road and Fowler Avenue
- widened the roadway between Fowler Avenue and Fletcher Avenue to provide five-foot paved shoulders on both sides of the road
• added an eight-foot-wide shared-use path between Fisherman's Point and 127th Avenue
- eliminated the gaps in the existing sidewalk between 127th Avenue and Fletcher Avenue
Project numbers 439532-1 and 439532-2 were combined into a single construction contract. All updates for both project numbers will be posted on this page.