| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | from Davis Road to Fletcher Avenue |
| Project Start | March 2021 |
| Length | 2.2 miles |
| City | Temple Terrace |
| County | Hillsborough |
| Construction Cost | $4.5 million |
| Estimated Completion | Late 2022 |
| Contractor | Ranger Construction Industries, Inc. |
Contact Information
Project Information Andrew Williams 813-612-3200 Andrew.Williams@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
As of Monday, October 31, 2022, all construction activities associated with this project have been completed.
This project repaved Morris Bridge Road between Davis Road and Fletcher Avenue in Temple Terrace.
Other improvements:
Project numbers 439532-1 and 439532-2 were combined into a single construction contract. All updates for both project numbers will be posted on this page.