Morris Bridge Road Repaving from Davis Road to Fletcher Avenue 439532-1-52-01
| Project Details |
| Work Type | Repaving |
|---|
| Phase | Completed |
|---|
| Limits | from Davis Road to Fletcher Avenue |
|---|
| Project Start | March 2021 |
|---|
| Length | 2.2 miles |
|---|
| City | Temple Terrace |
|---|
| County | Hillsborough |
|---|
| Construction Cost | $4.5 million |
|---|
| Estimated Completion | Late 2022 |
|---|
| Contractor | Ranger Construction Industries, Inc. |
|---|
Contact Information
Project Information
Andrew Williams
813-612-3200
Andrew.Williams@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
As of Monday, October 31, 2022, all construction activities associated with this project have been completed.
This project repaved Morris Bridge Road between Davis Road and Fletcher Avenue in Temple Terrace.
Other improvements:
added a six-foot sidewalk along the west side of the road between Davis Road and Fowler Avenue
widened the roadway between Fowler Avenue and Fletcher Avenue to provide five-foot paved shoulders on both sides of the road
added an eight-foot-wide shared-use path between Fisherman's Point and 127th Avenue
eliminated the gaps in the existing sidewalk between 127th Avenue and Fletcher Avenue
Project numbers 439532-1 and 439532-2 were combined into a single construction contract. All updates for both project numbers will be posted on this page.