I-75 Northbound Rest Area Replacement in southern Hillsborough County 437638-1-52-01
| Project Details |
| Work Type | Rest Area Replacement |
|---|
| Phase | Completed |
|---|
| Limits | I-75 NB Rest Area in Hillsborough County |
|---|
| Project Start | June 2019 |
|---|
| City | Ruskin |
|---|
| County | Hillsborough |
|---|
| Road | I-75 |
|---|
| Construction Cost | $17.5 million |
|---|
| Estimated Completion | Fall 2021 |
|---|
| Contractor | PCS Civil, Inc. |
|---|
Contact Information
Project Information
Anna Geismar 813-975-3553
Anna.Geismar@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
As of Wednesday, November 3, 2021, all construction activities associated with this project have been completed.
The rest area is now open!
This design-build project is replaced the existing northbound I-75 rest area at mile marker 238 in Hillsborough County.
Improvements included the demolition of the existing structures and the construction of new buildings, parking areas, dog parks, picnic pavilions, lighting, and other improvements.