US 301 Repaving from Lake St Charles Blvd to Progress Blvd/Bloomingdale Ave & NB I-75 On-ramp Improvements 441388-1-52-01

Project Details
Work TypeRepaving
PhaseCompleted
Limitsfrom Lake St Charles Blvd to Progress Blvd/Bloomingdale Avenue and the northbound I-75 On-ramp from US 301
Project StartAugust 4, 2021
Length1.5 miles
CityRiverview
CountyHillsborough
RoadUS 301
Construction Cost$21.4 million
Estimated CompletionSummer 2023
ContractorAjax Paving Industries of Florida, LLC

About

All construction activities associated with this project were completed on Friday, July 28, 2023.

Contact Information

Project Information

Maricelle Venegas 813-975-6204 roadwork@dot.state.fl.us

This design-build project repaved US 301 between Lake St. Charles Boulevard and Progress Boulevard/Bloomingdale Avenue in Riverview.

Additional improvements:

  • replaced the asphalt pavement with a durable concrete surface at the intersection of US 301 and Progress Boulevard/Bloomindale Avenue.
  • added a through lane to westbound Bloomingdale Avenue.
  • added sidewalk along the east side of US 301.
  • widened the northbound I-75 on-ramp from US 301.

This project was combined with 427454-3 into a single construction contract.

Media Contact

Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us