I-275 Causeway Seawall and Trail from Reo St to Howard Frankland Bridge 447534-1-52-01

Project Details
Work TypeSeawall and Trail
PhaseCompleted
Limitsfrom Reo Street to Howard Frankland Bridge
Project StartMarch 27, 2023
Length1.5 miles
CityTampa
CountyHillsborough
RoadI-275
Construction Cost$40.9 million
Estimated CompletionLate 2025
ContractorMasTec Civil, LLC

About

All construction activities associated with this project were completed on Friday, November 14, 2025.

This project constructed a seawall and shared-use path along the northside of I-275 between Reo Street and the Howard Frankland Bridge.

Completed travel lanes will connect from the Westshore Interchange to southbound I-275 as part of this project.

Construction activities began March 27, 2023, and finished on November 14, 2025.