| Project Details | |
| Work Type | Resurfacing |
|---|---|
| Phase | Construction |
| Limits | SR 39 from north of Central Avenue to US 301/Gall Boulevard |
| Project Start | December 1, 2025 |
| Length | 2.769 Miles |
| City | Crystal Springs |
| County | Pasco |
| Road | SR 39 |
| Construction Cost | $5.2 million |
| Estimated Completion | Fall 2026 |
| Contractor | Pigott Asphalt and Sitework LLC |
Contact Information
Project Information
John McShaffrey 813-975-6930 john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
Improvement to this roadway segment will include milling and resurfacing, minor widening and drainage upgrades, sidewalk repairs/minor reconstruction, curb and gutter repairs/minor reconstruction, signing and pavement markings, traffic signal head replacements/enhancements at Chancey Road, and performing general safety upgrades along SR 39 in Pasco County.
Construction began in December 2025.
For more information on this project, or to sign-up to receive construction updates and traffic alerts, please visit FDOTtampabay.com (Project Number: 447951-1-52-01) Last Updated: 02/10/2026