Alt US 19 (5th Avenue N) Repaving from 6th Street N to 58th Street N 448036-1-52-01

Project Details
Work TypeRepaving
PhaseCompleted
LimitsFrom west of 6th Street to Tyrone Boulevard
Project StartJanuary 4, 2024
Length4.5 miles
CitySt. Petersburg
CountyPinellas
Road5th Avenue North Alt US 19
Construction Cost$13 million
Estimated CompletionSummer 2025
ContractorAjax Paving Industries of Florida, LLC

About

As of July 22, 2025, all construction activities associated with this project have been completed.

This project repaved Alt. US 19 (5th Avenue North) from west of 6th Street North to 58th Street North in St. Petersburg.

Other improvements included sidewalk enhancements, median modifications, and the addition of bicycle lanes from 6th Street North to 20th Street North.

Construction is expected to be complete in summer 2025.

Contact Information

Project Information

Bryce Johns 727-575-8334

Bryce.Johns@dot.state.fl.us

Media Contact

Kayla Mejia 813-975-6060

Kayla.Mejia@dot.state.fl.us