| Project Details |
| Work Type | Widening and Realignment |
|---|
| Phase | Construction |
|---|
| Limits | from the Polk County line to US 301 at Clinton Avenue |
|---|
| Project Start | August 8, 2023 |
|---|
| Length | 8.7 miles |
|---|
| City | Dade City |
|---|
| County | Pasco |
|---|
| Road | US 98 |
|---|
| Construction Cost | $146.7 million |
|---|
| Estimated Completion | Fall 2028 |
|---|
| Contractor | Prince-Ajax US 98 Constructors |
|---|
| Contact Information |
| Project Information
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us |
| Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us |
For more information on this project, or to sign-up to receive construction updates and traffic alerts, please visit FDOTtampabay.com (Project Number: 443368-3-52-01) Last Updated: 08/31/2026