| EVALUATION CRITERIA | NO BUILD ALTERNATIVE | BUILD ALTERNATIVE |
| Purpose and Need |
| Accommodate Future Travel Demand | No | Yes |
| Improve Safety | No | Yes |
| Right-of-Way Impacts |
| Number of Parcels Impacted | 0 | 4 |
| Number of Residential Relocations | 0 | 0 |
| Number of Business Relocations | 0 | 0 |
| Potential Environmental Impacts |
| Protected Species | 0 | 1 |
| Archaeological Potential | None | Low |
| Historic Sites | 0 | 0 |
| Contamination Sites | 0 | 1 |
| Wetlands (Acres) | 0 | 42 |
| Floodplains (Acres) | 0 | 0.16 |
| Public Lands (Acres) | 0 | 0 |
| Noise Sensitive Sites | None | 135 |
| Estimated Costs in Millions (Present Day Costs) |
| Right of way | No cost | $10.7 |
| Wetland Mitigation | No cost | $1.9 |
| Construction Engineering and Inspection | No cost | $13.4 |
| Construction Cost | No cost | $191.9 |
Project costs are subject to change