EVALUATION MATRIX
EVALUATION CRITERIANO BUILD ALTERNATIVEBUILD ALTERNATIVE
Purpose and Need
Accommodate Future Travel DemandNoYes
Improve SafetyNoYes
Right-of-Way Impacts
Number of Parcels Impacted04
Number of Residential Relocations00
Number of Business Relocations00
Potential Environmental Impacts
Protected Species01
Archaeological PotentialNoneLow
Historic Sites00
Contamination Sites01
Wetlands (Acres)042
Floodplains (Acres)00.16
Public Lands (Acres)00
Noise Sensitive SitesNone135
Estimated Costs in Millions (Present Day Costs)
Right of wayNo cost$10.7
Wetland MitigationNo cost$1.9
Construction Engineering and InspectionNo cost$13.4
Construction CostNo cost$191.9
Project costs are subject to change