| Project Details | |
| Work Type | Interchange Improvements |
|---|---|
| Phase | Completed |
| Limits | Thonotosassa Road (SR 566) and I-4 Exit 19 |
| Project Start | September 11, 2024 |
| Length | .596 miles |
| City | Plant City |
| County | Hillsborough |
| Road | I-4 SR 566 Thonotosassa Road |
| Estimated Completion | Summer 2026 |
| Contractor | Watson Civil Construction, Inc. |
All construction activities associated with this project were completed on Monday, August 31, 2026.
This project widened SR 566 (Thonotosassa Road) from two to four lanes between the I-4 ramps, added a new northbound right turn lane onto eastbound I-4 entrance ramp, and installed a new traffic signal at the base of the off ramp from westbound I-4.
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us