62nd Street North Access Improvements from Columbus Drive to CSX Intermodal Center 433071-2-52-01

Project Details
Work TypeAccess Improvements
PhaseCompleted
Limitsfrom Columbus Drive to CSX Intermodal Center
Project StartFebruary 20, 2023
Length.5 miles
CityTampa
CountyHillsborough
Road62nd Street
Construction Cost$6 million
Estimated CompletionSummer 2024
ContractorWatson Civil Construction, Inc.

About

All construction activities associated with this project were completed on Wednesday, March 6, 2024.

The Florida Department of Transportation's contractor, Watson Civil Construction, Inc., repaved 62nd Street North from Columbus Drive to the CSX Intermodal Center in Tampa.

Other improvements included replacing the existing drainage ditch with a closed reinforced concrete pipe system, adding bike lanes, and installing sidewalks.