===== PAGE 1 =====
######## U.S. 41 (S.R. 45) Pavement Reconstruction at S.R. 44 450545-1-52-01
| Project Details |
| Work Type | Pavement Reconstruction |
| Phase | Design |
| Limits | U.S. 41 (S.R. 45) from south of S.R. 44 to north of S.R. 44 |
| Length | 0.19 miles |
| City | Inverness |
| County | Citrus |
| Road | SR 45 US 41 |
| Contact Information |
| Design Manager |
| Dinyar Sharifabad (813) 975-6172 | Dinyar.Sharifabad@dot.state.fl.us |
| Media Contact |
| Kayla Mejia 813-975-6060 | Kayla.Mejia@dot.state.fl.us |
Map data ©2025
## About
This project will mill the existing asphalt pavement and resurface with concrete pavement along U.S. 41 (State Road (S.R.)) 45) from south of S.R. 44 to north of S.R. 44 in Inverness.
Construction is anticipated to begin June 2028.