| Project Details |
| Work Type | New Interchange |
|---|
| Phase | Completed |
|---|
| Limits | From Old PascoRoad to BoyetteRd on OverpassRoad |
|---|
| Project Start | October 2020 |
|---|
| Length | .9 miles |
|---|
| City | Wesley Chapel |
|---|
| County | Pasco |
|---|
| Road | I-75 |
|---|
| Construction Cost | $65 million |
|---|
| Estimated Completion | Spring 2023 |
|---|
| Contractor | The Middlesex Corporation |
|---|
As of May 15, 2023, all work was completed and this project was final-accepted from the contractor.
The new diamond interchange includes a flyover ramp for westbound Overpass Road access onto southbound I-75.
To accommodate the new interchange, Overpass Road was widened from two lanes to four lanes between the interstate and Old Pasco Road and six lanes between the interstate and Boyette Road. Blair Drive was realigned to connect with Old Pasco Road. McKendree Road was realigned to connect with Boyette Road.
Contact Information
Project Information
John McShaffrey 813-975-6930 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
This design-build project constructed a new interstate interchange on I-75 at Overpass Road, approximately 3.5 miles south of SR 52 in Pasco County.
Sidewalks were built along Overpass Road. A 10-foot wide sidewalk was constructed on the north side of Overpass Road (next to the westbound traffic lanes) and a 6-foot wide sidewalk was built on the south side (next to the eastbound traffic lanes).