| Project Details | |
| Work Type | Repaving |
|---|---|
| Phase | Completed |
| Limits | from north of Fletcher Avenue to south of Van Dyke Road |
| Project Start | August 4, 2022 |
| Length | 4.3 miles |
| City | Tampa |
| County | Hillsborough |
| Road | Dale Mabry Highway SR 597 |
| Construction Cost | $8.4 million |
| Estimated Completion | Summer 2023 |
| Contractor | Preferred Materials, Inc. |
Contact Information
Project Information
Maricelle Venegas 813-975-6204 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
All construction activities associated with this project were completed on Friday, July 21, 2023.
This project repaved Dale Mabry Highway (SR 597) between Fletcher Avenue and Van Dyke Road in Hillsborough County.
Other improvements included replacing the traffic signal at Bearss Avenue.
Construction activities were completed during summer of 2023.
*Construction cost includes original construction contract amount plus approved contract changes. It does not include inspection oversite.