Tampa Bay Florida Department of Transportation
SR 597 (Dale Mabry Highway) Repaving from Fletcher Avenue to Van Dyke Road 440253-1-52-01
Project Details
Work TypeRepaving
PhaseCompleted
Limitsfrom north of Fletcher Avenue to south of Van Dyke Road
Project StartAugust 4, 2022
Length4.3 miles
CityTampa
CountyHillsborough
RoadDale Mabry Highway SR 597
Construction Cost$8.4 million
Estimated CompletionSummer 2023
ContractorPreferred Materials, Inc.
Contact Information
Project Information
Maricelle Venegas 813-975-6204 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
About
All construction activities associated with this project were completed on Friday, July 21, 2023.
This project repaved Dale Mabry Highway (SR 597) between Fletcher Avenue and Van Dyke Road in Hillsborough County.
Other improvements included replacing the traffic signal at Bearss Avenue.
Construction activities were completed during summer of 2023.
*Construction cost includes original construction contract amount plus approved contract changes. It does not include inspection oversite.