CR 52 Repaving from Storch Lane to US 98/US 301 and CR 52 Roundabout at College Ave./Pompanic St. 439832-1-52-01 and 439832-3-52-01
| Project Details |
| Work Type | Roundabout |
|---|
| Phase | Completed |
|---|
| Length | 8 miles |
|---|
| City | Dade CitySan AntonioSt. Leo |
|---|
| County | Pasco |
|---|
| Road | CR 52 |
|---|
| ConstructionCost | $10.2 million |
|---|
| EstimatedCompletion | Summer 2025 |
|---|
| Contractor | Watson Civil Construction, Inc. |
|---|
Contact Information
Project Information
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us
As of June 23, 2025, all construction activities associated with this project have been completed.
Two projects were combined to be built under one design-build construction project:
Resurfacing of CR 52 from west of Storch Lane to US 98/US 301 (439832-1-52-01); and
CR 52 at College Avenue / Pompanic Street Roundabout (439832-3-52-01).
The project repaved CR 52 (formerly SR 52) from west of Storch Lane in San Antonio to east of Smith Road in Dade City, and from south of Center Avenue to US 98/US 301 in Dade City. Resurfacing from east of Smith Road to south of Center Avenue was done under a previous project (429076-4).
A roundabout was constructed at the intersection of CR 52 and College Avenue / Pompanic Street in the City of San Antonio. City of San Antonio utilities were also relocated for the roundabout.
Here is a cost breakout for construction of each of the three major portions of the construction project:
CR 52 milling and resurfacing (project 439832-1-52-01); $7.2 million.
CR 52 & College/Pompanic Roundabout (project 439832-3-52-01): $2.7 million
City of San Antonio Utility relocations for roundabout (project 439832-3-56-01): $280,500