CR 582A (Morris Bridge Road) New Traffic Signal at SB I-75 Entrance Ramp 254677-5-40
| Project Details |
| Work Type | Safety Improvements |
|---|
| Phase | Completed |
|---|
| Limits | Fletcher Avenue and I-75 SB Exit Ramp |
|---|
| Project Start | Summer 2024 |
|---|
| City | Tampa Temple Terrace |
|---|
| County | Hillsborough |
|---|
| Road | Fletcher Avenue |
|---|
| Construction Cost | $900,000 |
|---|
| Estimated Completion | Spring 2025 |
|---|
| Contractor | Cone & Graham, Inc. |
|---|
Construction is underway and expected to be complete in spring 2025.
*****
*****
Contact Information
Project Information
Maddie Griffin 727-575-8334
roadwork@dot.state.fl.us
The Florida Department of Transportation's Design-Build firm, Cone & Graham, Inc., is installing a new traffic signal at Morris Bridge Road (CR 582A) onto the southbound I-75 entrance ramp in Hillsborough County.
Other safety and operational improvements include roadway resurfacing, installing sidewalk, and extending the westbound left-turn lane from Fletcher Avenue onto the I-75 southbound entrance ramp.
What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project. The contract work covers from initial design through construction completion. This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously.