| Project Details |
| Work Type | Widening |
|---|
| Phase | Completed |
|---|
| Limits | From Jump Court to Fort Island Trail |
|---|
| Project Start | November 2018 |
|---|
| Length | 4.7 miles |
|---|
| City | Crystal River Homosassa Springs |
|---|
| County | Citrus |
|---|
| Road | US 19 |
|---|
| Construction Cost | $53.8 million |
|---|
| Estimated Completion | May 15, 2026 |
|---|
As of May 15, 2026, all construction activities associated with this project have been completed.
This project widened US 19 from four lanes to six lanes between S. Jump Court and W. Fort Island Trail in Citrus County. All roadwork was completed as of May 19, 2025.
A shared use path, sidewalks, and storm water ponds were also constructed with this project.
Contact Information
Project Information
John McShaffrey 813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
March 20, 2025 -- As of May 19, 2025, asphalt paving was completed on southbound US 19 from south of W Ozello Trail to S Jump Court. All lanes are now open to traffic in both directions of US 19 in the project limits.
All northbound US 19 lanes were open to traffic as of September 20, 2024.