Tampa Bay Florida Department of Transportation
US 19 Widening from Jump Court to Fort Island Trail 405822-3-52-01
Project Details
Work TypeWidening
PhaseCompleted
LimitsFrom Jump Court to Fort Island Trail
Project StartNovember 2018
Length4.7 miles
CityCrystal River Homosassa Springs
CountyCitrus
RoadUS 19
Construction Cost$53.8 million
Estimated CompletionMay 15, 2026
About
As of May 15, 2026, all construction activities associated with this project have been completed.
This project widened US 19 from four lanes to six lanes between S. Jump Court and W. Fort Island Trail in Citrus County. All roadwork was completed as of May 19, 2025.
A shared use path, sidewalks, and storm water ponds were also constructed with this project.
Contact Information
Project Information
John McShaffrey 813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
Progress Update > All lanes are open!
March 20, 2025 -- As of May 19, 2025, asphalt paving was completed on southbound US 19 from south of W Ozello Trail to S Jump Court. All lanes are now open to traffic in both directions of US 19 in the project limits.
All northbound US 19 lanes were open to traffic as of September 20, 2024.