# SR 693 (Pasadena Ave) Repaving from Matthews Rd/Shore Dr. to Central Ave. 440254-2-52-01
| Project Details |
| Work Type | Repaving and Business Access Transit (BAT) lane |
| Phase | Completed |
| Limits | from north of Matthews Rd/Shore Dr. to south of Central Ave. |
| Project Start | Fall 2021 |
| City | South Pasadena St. Petersburg |
| County | Pinellas |
| Road | Pasadena Avenue SR 693 |
| Construction Cost | $1.6 million |
| Estimated Completion | Spring 2022 |
| Contractor | Preferred Materials, Inc. |
| Contact Information |
| Project Information |
| Matt Kappler | 727-575-8300 |
| matthew.kappler@dot.state.fl.us |
| Media Contact |
| Kayla Mejia | 813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
Map data ©2022 Google, INEGI
## About
All construction activities associated with this project were completed on May 15, 2022.
This project will repave Pasadena Ave. and add a Business Access Transit (BAT) lane for bus rapid transit.
Construction activities are anticipated to begin in the fall of 2021 and be complete in the Spring of 2022.