===== PAGE 1 ===== ## I-75 at SR 52 Interchange Improvements 454668-1-52-01
Project Details
Work TypeInterchange Improvement
PhaseCompleted
LimitsI-75 and SR 52 interchange area
Project StartApril 26, 2026
CitySan Antonio
CountyPasco
RoadI-75 SR 52
Construction Cost$2.1 million
Estimated CompletionOctober 17, 2026
ContractorC.W. Roberts Contracting, Incorporated
Contact Information Project Information John McShaffrey 813-975-6930 john.mcshaffrey@dot.state.fl.us Media Contact Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
Image
Map data ©2026 Google ## About As of October 17, 2026, all construction activities associated with this project have been completed. Interchange improvements that were constructed with this project included the following: - Re-striped the existing pavement to provide a 2-lane northbound I-75 exit ramp to SR 52. • Provided a 2-lane ramp from westbound SR 52 to the southbound I-75 entrance ramp. • Provided dual left turn lanes from eastbound SR 52 to the entrance ramp onto northbound I-75. • Provided two receiving lanes on the northbound I-75 entrance ramp. • Reconfigured the existing lanes on westbound SR 52 from Pasco Road to I-75 accordingly.