| Project Details | |
| Work Type | Interchange Improvement |
|---|---|
| Phase | Completed |
| Limits | I-75 and SR 52 interchange area |
| Project Start | April 26, 2026 |
| City | San Antonio |
| County | Pasco |
| Road | I-75 SR 52 |
| Construction Cost | $2.1 million |
| Estimated Completion | October 17, 2026 |
| Contractor | C.W. Roberts Contracting, Incorporated |
As of October 17, 2026, all construction activities associated with this project have been completed.
Interchange improvements that were constructed with this project included the following:
Contact Information
Project Information John McShaffrey 813-975-6930 john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia
813-975-6060
Kayla.Mejia@dot.state.fl.us