===== PAGE 1 ===== # SR 52 Widening from the Suncoast Parkway to east of US 41 256323-1-52-01
Project Details
Work TypeWidening
PhaseCompleted
LimitsFrom the Suncoast Parkway to east of US 41
Project StartSeptember 2019
Length3.8 miles
CityLand O' Lakes
CountyPasco
RoadSR 52 US 41
Construction Cost$54.8 million
Estimated CompletionEarly 2025
ContractorPCS Civil, Inc.
Contact Information
Project Information
John McShaffrey813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060
Kayla.Mejia@dot.state.fl.us
Image
## About The project was accepted from the contractor as completed on January 29, 2025 This project widened SR 52 to a six-lane divided highway from the Suncoast Parkway to east of US 41 and approximately one mile total of widening on US 41 approaching the SR 52 intersection in each direction. The intersection of SR 52 and US 41 was rebuilt in concrete to better handle truck starts, stops, and turning movements. This project tied into the US 41 widening project that was completed in October 2023. A 12-foot-wide multi-use trail was constructed along the north side of SR 52. * Construction cost includes original construction contract amount plus approved contract changes. It does not include inspection oversite.