| Project Details | |
| Work Type | Safety Improvements |
|---|---|
| Phase | Completed |
| Limits | at Marine Parkway |
| City | New Port Richey |
| County | Pasco |
| Road | US 19 |
| Construction Cost | $591,000 |
| Estimated Completion | Spring 2026 |
| Contractor | Cone & Graham, Inc. |
As of April 13, 2026, all construction activities associated with this project have been completed.
The Florida Department of Transportation's Design-Build Firm, Cone & Graham, Inc., is making roadway improvements by extending the two left turn lanes on US 19 at Marine Parkway in Pasco County.
Construction activities are expected to complete summer 2026.
Contact Information
Project Information Maddie Griffin 727-575-8334 Maddie.Griffin@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
***** *****
What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project. The contract work covers from initial design through construction completion. This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously.