===== PAGE 1 ===== # Reo Street Widening and Repaving from Cypress Street to Gray Street 447615-1-52-01
Project Details
Work TypeRoad Widening and New Sidewalk
PhaseCompleted
Limitsfrom Cypress St to Gray St
Project StartJanuary 2024
Length.428 miles
CityTampa
CountyHillsborough
Construction Cost$6.1 million
Estimated CompletionSpring 2025
ContractorPCS Civil, Inc.
Contact Information
Project Information
Maricelle Venegas813-975-6204
RoadWork@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060
Kayla.Mejia@dot.state.fl.us
Image
Map data ©2025 Google ## About All construction activities associated with this project were completed on Monday, April 28, 2025. This project widened Reo Street from a two-lane road to a four-lane road from Cypress Street to Gray Street in Tampa. The newly widened roadway has two southbound lanes, one northbound lane, and along the center a two-way turn lane. Improvements to the intersection of Cypress Street and Reo Street included adding an eastbound right turn lane, a westbound left turn lane, and installing a new traffic signal. In addition, a 10-foot-wide sidewalk was added along Reo Street from Gray Street to Cypress Point Park.