# US 41 Resurfacing from south of County Line Rd. to south of Powell Rd. 447935-1-52-01
| Project Details |
| Work Type | Resurfacing |
| Phase | Construction |
| Limits | From south of County Line Rd. to south of Powell Rd |
| Project Start | late 2026 |
| Length | 4.4 Miles |
| City | Masaryktown |
| County | Hernando |
| Road | Broad Street US 41 |
| Construction Cost | $7.93 million |
| Estimated Completion | summer 2027 |
| Contractor | C.W. Roberts Contracting, Inc. |
| Contact Information |
| Project Information |
| John McShaffrey\n813-975-6930 | john.mcshaffrey@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 | Kayla.Mejia@dot.state.fl.us |
Map data ©2026 Google
## About
This project includes the resurfacing of US 41 from south of County Line Road (Pasco/Hernando County Line) to south of Powell Road in Hernando County.
The project will also improve current ADA facilities, extend the left turn lanes at US 41 to access Ayers Road, and construct a new right turn lane at Ayers Road to access northbound US 41. Other improvements include minor drainage modifications, signalization, signing and pavement markings, and lighting.
Construction is currently anticipated to begin in late 2026.