===== PAGE 1 =====
## SR 60 (Adamo Drive) Intersection Improvements at Maydell Drive 453420-1-32-01
| Project Details |
| Work Type | Signalization and Intersection Improvements |
| Phase | Construction |
| Limits | SR 60 at Maydell Drive |
| Project Start | October 14, 2026 |
| Length | 0.2 miles |
| City | Tampa |
| County | Hillsborough |
| Road | Adamo Drive SR 60 |
| Construction Cost | $1 million |
| Estimated Completion | Spring 2027 |
| Contractor | Sun Civil, LLC |
| Contact Information |
| Project Information |
| Maricelle Venegas\n813-975-6204 |
| Maricelle.Venegas@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 |
| Kayla.Mejia@dot.state.fl.us |
## About
Intersections improvements have begun to SR 60 (Adamo Drive) at Maydell Drive in Tampa, Hillsborough County.
Improvements include:
• Installing new traffic signal
• Adding pedestrian signals and crosswalks
• Upgrading intersection lighting
Construction activities are expected to finish spring 2027.