## US 301 at Wire Road -- New Traffic Signal 455145-1-52-01
| Project Details |
| Work Type | Traffic Signal Installation and Intersection Improvement |
| Phase | Construction |
| Limits | Intersection of US 301 at Wire Road |
| Project Start | May 11, 2026 |
| Length | 1,200 feet (0.23 mile) |
| City | Zephyrhills |
| County | Pasco |
| Road | US 301 |
| Construction Cost | $1.7 million |
| Estimated Completion | late 2026 / early 2027 |
| Contractor | Cone & Graham, Inc. |
| Contact Information |
| Project Information |
| John McShaffrey\n813-975-6930 | john.mcshaffrey@dot.state.fl.us |
| Media Contact |
| Kayla Mejia\n813-975-6060 | Kayla.Mejia@dot.state.fl.us |
Map data ©2025 Google
## About
This project will install a new traffic signal at the US 301 / Wire Road intersection. The project will also include the construction of a new northbound left turn lane due to the high volume of U-turns. Pedestrian crosswalks and roadway lighting will also be built as part of this project.
Construction began May 11, 2026.