===== PAGE 1 ===== ## US 301 at Wire Road -- New Traffic Signal 455145-1-52-01
Project Details
Work TypeTraffic Signal Installation and Intersection Improvement
PhaseConstruction
LimitsIntersection of US 301 at Wire Road
Project StartMay 11, 2026
Length1,200 feet (0.23 mile)
CityZephyrhills
CountyPasco
RoadUS 301
Construction Cost$1.7 million
Estimated Completionlate 2026 / early 2027
ContractorCone & Graham, Inc.
Contact Information
Project Information
John McShaffrey\n813-975-6930john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia\n813-975-6060Kayla.Mejia@dot.state.fl.us
Image
Map data ©2025 Google ## About This project will install a new traffic signal at the US 301 / Wire Road intersection. The project will also include the construction of a new northbound left turn lane due to the high volume of U-turns. Pedestrian crosswalks and roadway lighting will also be built as part of this project. Construction began May 11, 2026.