Tampa Bay Florida Department of Transportation
SR 553 (Park Road) Repaving from US 92 (Baker Street) to north of I-4 441664-1-52-01
Project Details
Work TypeRepaving
PhaseCompleted
Limitsfrom US 92 (Baker Street) to north of I-4
Project StartAugust 15, 2025
Length1.14 Miles
CityPlant City
CountyHillsborough
RoadSR 553
Construction Cost$4.6 million
Estimated CompletionFall 2026
ContractorHubbard Construction Company
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
About
All construction activities associated with this project were completed on Saturday, October 17, 2026.
This project repaved Park Road (SR 553) from Baker Street to north of I-4 in Plant City.
Additional improvements included the installation of sidewalk, signing, pavement markings, signalization, lighting, and utility adjustments.
The $4.6 million repaving project was expected to finish fall of 2026.