| Project Details | |
| Work Type | Operational Improvements |
|---|---|
| Phase | Completed |
| Project Start | October 24, 2022 |
| County | Citrus Pasco Pinellas |
| Road | Paul Buchman Highway SR 39 SR 580 SR 584 Tampa Road |
| Construction Cost | $500,000 |
| Estimated Completion | Fall 2023 |
Contact Information
Project Information
Maddie Pfingsten 727-575-8334 roadwork@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
As of August 3, 2023, all construction activities associated with this project have been completed.
This safety project will enhance operational improvements at three separate locations in Citrus, Pasco, and Pinellas counties.
Improvements include:
Construction is expected to be completed in fall 2023.