SR 580 (Busch Boulevard) Corridor Improvements from N Dale Mabry Highway to Nebraska Avenue 435908-2-52-01 & 435908-2-52-02
| Project Details | |
| Work Type | Urban Corridor and Safety Improvements |
|---|---|
| Phase | Construction |
| Limits | SR 580 (Busch Boulevard) from N Dale Mabry Highway to Nebraska Avenue |
| Project Start | Early 2027 |
| Length | 3.7 miles |
| City | Tampa |
| County | Hillsborough |
| Road | Busch Boulevard SR 580 |
| Construction Cost | $12.8 million |
| Estimated Completion | Late 2027 |
| Contractor | C.W. Roberts Contracting, Inc. |
Contact Information
Project Information
Maricelle Venegas 813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060
Kayla.Mejia@dot.state.fl.us
This project will improve the urban corridor on SR 580 (Busch Blvd) from N Dale Mabry Hwy to Nebraska Avenue in Tampa, Hillsborough County.
Key improvements within the project limits include:
Construction is anticipated to begin in early 2026.