===== PAGE 1 ===== ### SR 580 (Dale Mabry Highway) Intersection Lighting Upgrades at W. Humphrey Street 254677-5-07
Project Details
Work TypeSafety Improvements
PhaseCompleted
LimitsDaley Mabry\nHwy at\nHumphrey St
Project StartNovember 8, 2021
CityTampa
CountyHillsborough
RoadDale Mabry\nHighway
Construction Cost$73,575.31
Estimated CompletionEarly 2022
ContractorCone & Graham, Inc.
Contact Information
Project Information
Randy Aebersold727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kayla Mejia813-975-6060
Kayla.Mejia@dot.state.fl.us
Image
## About As of January 12, 2022 all construction activities associated with this project have been completed. This design-build project is making improvements to roadway lighting at Dale Mabry Highway (SR 580) and W. Humphrey Street in Hillsborough County. Improvements include retrofitting existing roadway lighting fixtures with LED luminaries and installation of new light poles hardware as necessary to light the roadway to current standards. Construction is expected to finish in early 2022.