SR 44 (Gulf to Lake Highway) Resurfacing from W Homosassa Trail to N Central Avenue
457613-1-52-01
| Project Details |
| Work Type | Milling and Resurfacing |
|---|
| Phase | Construction |
|---|
| Limits | SR 44 (Gulf to Lake Highway) from W Homosassa Trail to N Central Avenue |
|---|
| Project Start | September 22, 2026 |
|---|
| City | Inverness Lecanto |
|---|
| County | Citrus |
|---|
| Road | Gulf To Lake Highway (Citrus) SR 44 |
|---|
| Construction Cost | $1.3 million |
|---|
| Estimated Completion | Spring 2027 |
|---|
Contact Information
Project Information
John McShaffrey 813-975-6930 john.mcshaffrey@dot.state.fl.us
Media Contact
Kayla Mejia 813-975-6060 Kayla.Mejia@dot.state.fl.us
The purpose of this project is to preserve and extend the life of the existing pavement through milling and resurfacing selected areas along this section of State Road 44 in Citrus County. The top layer of asphalt (friction course) will be milled and repaved in approximately 12 areas between W Homosassa Trail in the Lecanto area and N Central Avenue in Inverness. While the total distance of this stretch of highway is about 8.5 miles, only about 1.4 miles of pavement needs replacement and will be milled and resurfaced during this project.
This is a design-build project, which is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT to fully design and construct the project. The contract work includes initial design through construction completion. This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously.
The design portion of the project is underway as of September 22, 2026. Construction is expected to begin in late November to early December 2026.
For more information on this project, or to sign-up to receive construction updates and traffic alerts, please visit FDOTtampabay.com (Project Number: 457613-1-52-01) Last Updated: 09/23/2026