H:\PROJECTS\323617 < 323617 S04 GRADING PLAN >
KRISTIN 1/22/24 H:\PROJECTS\3236
CK_22LOT 8
KEY MAPSCALE: 1" = 2000'
22LOT 19
2 01/22/2024 REV PER PLANNING BOARD COMMENTS KNL
1 11/20/2023 GENERAL REVISIONS KNL
No. DATE DESCRIPTION BY
PDS PROFESSIONAL DESIGN SERVICES, L.L.C.
CONSULTING ENGINEERS, LAND SURVEYORS, PLANNERS, ENVIRONMENTAL SCIENTISTS, CONSTRUCTION SERVICES 1245 AIRPORT ROAD, SUITE 1, LAKEWOOD, NEW JERSEY 08701 PHONE 732 363 0060 FAX 732 363 0073 NEW JERSEY STATE BOARD OF P.E. & L.S. CERTIFICATE OF AUTHORIZATION NO.24GA28125400 IAN M BORDEN, PP N.J. PROFESSIONAL PLANNER LICENSE *33LJ00617400 IBORDEN*PDS-NJ.COM WILLIAM A. STEVENS, PE, PP PROFESSIONAL ENGINEER, NEW JERSEY LIC. *39915 PROFESSIONAL PLANNER, NEW JERSEY LIC. *5394 BSTEVEN*PDS-NJ.COM GRAHAM J. MACFARLANE, PE, PP, CME PROFESSIONAL ENGINEER, NEW JERSEY LIC. *37110 PROFESSIONAL PLANNER, NEW JERSEY LIC. *6104 GRAHAM*PDS-NJ.COM STEVEN METELSKI, JR., PLS N.J. PROFESSIONAL LAND SURVEYOR LICENSE *43393 STEVENM*PDS-NJ.COM
VILLIMINA. OIEVENO, III, r.E., P.P. PROFESSIONAL ENGINEER, NEW JERSEY LIC. #39915 PROFESSIONAL PLANNER, NEW JERSEY LIC. #5394 PRELIMINARY & FINAL SITE PLANS GRADING & STORM DRAINAGE PLAN FOR TAX BLOCK 22203 TAX LOT 11 TOWNSHIP OF JACKSON NEW JERSEY
OCEAN COUNTY
SCALE: 1" = 30" JOB NUMBER: 323617
DRAWN BY: KNL DATE: MARCH 17, 2023
THIS DOCUMENT AND THE IDEAS AND DESIGNS INCORPORATED HEREIN, AS AN INSTRUMENT OF PROFESSIONAL SERVICE, IS THE PROPERTY OF PROFESSIONAL DESIGN SERVICES, L.L.C., AND IS NOT TO BE USED IN WHOLE OR IN PART FOR ANY OTHER PRO- WITHOUT THE WRITTEN AUTHORIZATION OF PROFESSIONAL DESIGN SERVICES, L.L.C.
26.5056
STORMWATER BASIN NOTES:
LEGEND
Test PitsTP # 3Elevation = 72.2TP # 5Elevation = 75.5
TP # 1Elevation = 72.2
0 - 22"10 YR 4/6 Sand y Loam0 - 24"10 YR 4/6 Sandy Loam0 - 32"10 YR 4/4 Sandy Loam
22 - 63"10 YR 6/8 Loamy Sand24 - 44"10 YR 6/8 Loamy Sand32 - 50"10 YR 6/8 Sandy Loam
63 - 82"10 YR 7/7 Loamy Sand 6/8 distinct mottles44 - 65"10 YR 7/6 Loamy Sand50 - 60"10 YR 7/8 Loamy Sand
82 - 88"10 YR 5/1 Loam 5/8 mottles65 - 74"10 YR 7/6 Loamy Sand 6/8 mottles60 - 96"10 YR 4/6 Sandy Loam
88 - 120"10 YR 7/8 Coarse Sandy Loam 6/8 dist mottles74 - 106"10 YR 5/2 Sandy Loam 5/8 mottles96 - 105"10 YR 6/4 Sandy Loam 5/8 distinct mottles
106 - 112"Gley1 6/N Loam 10 YR 5/8 mottles105 - 114"5 Y 5/3 Clay Loam 5/8 mottles
112 - 128"10 YR 6/6 Sand 8/8 distinct mottles114 - 132"2.5 Y 6/4 Loamy Sand 5/8 distinct mottles
SHWT @ 63", Elevation 66.9
Groundwater found at 90"SHWT @ 65", Elevation = 66.8SHWT @ 96", Elevation = 67.5
Permeability @ 56" = 11.5 inches per hourWater @ 100"Permeability @ 120" = 5.5 Inches per hour
Permeability @ 118" = 13.0 inches per hourWater @ 108"
TP # 2Elevation = 72.7TP # 4Elevation = 74.2
0 - 4"GravelTP # 6Elevation = 73.0
4 - 28"10 YR 5/8 Loamy Sand0 - 4"10 YR 4/6 Sandy Loam
28 - 48"10 YR 6/8 Loamy Sand4 - 55"10 YR 5/8 Sandy Loam0 - 11"10 YR 4/4 Sandy Loam
48 - 65"10 YR 7/8 Loamy Sand55 - 79"10 YR 7/6 Loamy Sand11 - 23"10 YR 5/8 Sandy Loam
65 - 86"10 YR 8/8 Loamy Sand 5/8 mottles79 - 88"10 YR 8/4 Sandy Loam 5/8 mottles23 - 48"10 YR 6/8 Loamy Sand
86 - 120"10 YR 7/8 Sand 6/8 mottles88 - 99"5 Y 5/3 Clay Loam 5/8 mottles48 - 79"10 YR 8/8 Loamy Sand
99 - 108"5 Y 6/4 Sandy Loam 6/8 mottles79 - 89"Gley1 6/N Loam 10 YR 5/8 mottles
SHWT @ 65", Elevation 67.3108 - 120"10 YR 6/8 Loam Sand w/ Pea Gravel89 - 102"10 YR 7/8 Loamy San 5/8 distinct mottles
Groundwater found at 94"102 - 120"10 YR 8/3 Loamy Sand 5/8 distinct mottles
Permeability @ 60" = 10.5 Inches per hourSHWT @ 79", Elevation = 67.6
Water @ 102"SHWT @ 79", Elevation = 66.4
Permeability @ 116" = 18.5 Inches per hourPermeability @ 93" = 10.0 Inches per hour
Water @ 108"
THE PROJECT DOES NOT CONTAIN ANY HIGH POLLUTANT LOADING AREAS (HPLA) AND SECREGATION OR PRE-TREATMENT OF RUNOFF IS NOT REQUIRED.
THE STORMWATER BASIN AND RECHARGE SYSTEM HAS BEEN DESIGNED TO MAINTAIN A MINIMUM SEPARATION OF AT LEAST TWO (2) FEET FROM THE BASIN BOTTOM TO THE SEASONAL HIGH WATER TABLE.
THE SOIL PERMEABILITY BELOW THE BASIN DOES NOT PERMEATED IN EXCESS OF 20 INCHES PER HOUR AND NO BIORETENTION SYSTEM IS REQUIRED. UNSUITABLE SOILS MUST BE REMOVED AND REPLACED.
A GROUNDWATER MOUNDING ANALYSIS INDICATES NO ADVERSE IMPACT TO ADJACENT WATERBODIES, WETLANDS, STRUCTURES OR SEPTICS.
CARE MUST BE TAKEN DURING CONSTRUCTION TO MINIMIZE COMPACTION OF THE BASIN BOTTOM. THE BASIN AREA MUST BE RENOVATED AND TILLED AFTER CONSTRUCTION IS COMPLETED AND THE DRAINAGE AREA IS STABILIZED. NO EARTHWORK MAY BE PERFORMED WHEN SOIL MOISTURE CONTENT IS ABOVE THE LOWER PLASTIC LIMIT.
EXISTING SPOT GRADE127.32 × 115.10 +
PROPOSED SPOT GRADE115.10 +
EXISTING CONTOUR134
PROPOSED CONTOUR91
PROPOSED INLET■
PROPOSED STORM MANHOLE●
PROPOSED FLARED END SECTION▶
PROPOSED STORM PIPE------
PROPOSED ROOF DRAINAGE------
PROPOSED CLEAN OUT-
PROPOSED TEST PITImage
STORMWATER SYSTEM MAINTENANCE:
ALL MAINTENANCE FOR EACH STORMWATER MANAGEMENT SYSTEM WILL BE THE RESPONSIBILITY OF THE PROPERTY OWNER.
GRADING & DRAINAGE NOTES:
ALL HDPE STORM DRAINAGE TO BE NON PERFORATED HI-Q SURE LOK 2.0 HIGH STRENGTH PIPE WITH WATERTIGHT GASKETS AS MANUFACTURED BY HANCOR, OR EQUIVALENT UNLESS OTHERWISE NOTED.
ALL STORMWATER INLETS TO BE TYPE 'B' UNLESS OTHERWISE NOTED.
ALL BUILDING ROOF DRAINS WILL CONNECT TO THE STORMWATER DRAINAGE SYSTEM. ROOF DRAIN SYSTEM IS PRELIMINARY, PENDING THE COMPLETION OF FINAL ARCHITECTURAL DESIGN.
FOLLOWING IS A SUMMARY OF THE REQUIRED MAINTENANCE ACTIVITIES:
TASKSCHEDULE
INFILTRATION SYSTEM
DEBRIS REMOVALBI-ANNUALLY
INSPECTION & REPAIR (AS NECESSARY) OF STRUCTURESANNUALLY
TILLING OF BASIN BOTTOMANNUALLY
COLLECTION SYSTEMS
DEBRIS REMOVAL & CLEANINGBI-ANNUALLY
INSPECTION & REPAIR (AS NECESSARY) OF STRUCTURESANNUALLY
RAINAGE SYSTEM SHALL BE CLEANED BY THE APPLICANT UPON COMPLETION OF THE SITE.
COUNTY STORMWATER NOTES
AREA OF ADDITIONAL PAVEMENT ALONG WHITESVILLE ROAD IS 7,000 SQUARE FEET.
2. RUNOFF VOLUME OF WATER QUALITY STORM (1.25") FROM THE ADDITIONAL PAVEMENT AREAS IS 730 CUBIC FEET.
SCALE:1" = 30'JOB NUMBER:323617
DRAWN BY:KNLDATE:MARCH 17, 2023
DESIGN/CALC'D BY:IMBSHEET: 415
CHECKED BY:WAS
Test Pits performed by PDS April 13, 2023 Permeability results per Tube Permeameter Tests
TILLING AND/OR REPLACEMENT OF THE BASIN BOTTOM SHALL BE DONE WHEN THE CALCULATED PERMEABILITY RATES ARE NOT ACHIEVED.
3. THE RETENTION VOLUME OF THE UNDERGROUND RECHARGE SYSTEM IS 146 LF OR 745 CUBIC FEET. BLOCK 22 LOT 19