===== PAGE 1 =====
# FDOT Long Range Estimating System - Production R3: Project Details by Sequence Report
Project: 454217-1-52-01
Letting Date: 02/2029
Description: SR 5 (US 1) Resurfacing from SR 50 (Cheney Hwy) to SR 406 (Garden St), MP 0.000 to MP 4.117 & MP 35.686 to MP 35.699
District: 05 County: 70 BREVARD
Market Area: 08 Units: English
Contract Class: Lump Sum Project: N
Design/Build: N Project Length: 4.130 MI
Project Manager: HNTB/CB/RX
## Version 7-P Project Grand Total
$16,020,131.32
Description: SR 5 (US 1) from SR 50 (Cheney Hwy) to SR 406 (MP 0.000 to MP 4.117 & MP 35.686 to MP 35.699). (FY 28-32 Update 5/20/2026; Updated by KNHNTRX on 10/16/2025).
| Comment: Guardrail replacement and minor widening at SR 50, median modifications at several intersections |
| 110-4-10 | REMOVAL OF EXIST CONC | 294.00 SY | 46.00 | 13,524.00 |
| Comment: 10 curb ramp reconstructions for ADA in-kind (134 SY). 10 curb ramps for ADA reconstruction with additional impacts (160 SY). |
| 327-70-1 | MILLING EXIST ASPH PAVT, 1" AVG DEPTH | 2,518.00 SY | 4.25 | 10,701.50 |
| Comment: Deeper rehab for 5% of project. 50,350.08 x .05 = 2,518 SY |
| 327-70-4 | MILLING EXIST ASPH PAVT, 3" AVG DEPTH | 9,974.00 SY | 3.25 | 32,415.50 |
| Comment: 34 turn lanes × 11-ft (avg) × 240-ft long (avg) = 9,974 SY |
| 334-1-53 | SUPERPAVE ASPH CONC, TRAF C, PG76-22 | 962.00 TN | 160.00 | 153,920.00 |
| Comment: 1" for deeper rehab for 5% of project (2,518 × 110 / 2000 = 139 TN) 1.5" for 34 turn lanes (9974 × 165 /2000 = 823 TN) |
| 337-7-83 | ASPH CONC FC, TRAFFIC C,FC-12.5,PG 76-22 | 823.00 TN | 169.25 | 139,292.75 |
| Comment: 1.5" for 34 turn lanes (9974 × 165 /2000 = 823 TN) |
| 339-1 | MISCELLANEOUS ASPHALT PAVEMENT | 5.03 TN | 450.00 | 2,263.50 |
| Comment: For new guardrail at MP 35.643 RT |
| 520-1-10 | CONCRETE CURB & GUTTER, TYPE F | 455.00 LF | 52.25 | 23,773.75 |
| Comment: 20 curb ramps for ADA reconstruction, 18LF per ramp = 360 LF plus additional 95LF at SR 50 |
| 522-1 | CONCRETE SIDEWALK AND DRIVEWAYS, 4" | 40.00 SY | 86.00 | 3,440.00 |
| Comment: Sidewalk impacts due to ADA ramp reconstruction |
| 522-2 | CONCRETE SIDEWALK AND DRIVEWAYS, 6" | 200.00 SY | 117.00 | 23,400.00 |
| Comment: 20 curb ramps for ADA reconstruction (20 × 10SY each = 200 SY) |
| 527-2 | DETECTABLE WARNINGS | 300.00 SF | 35.00 | 10,500.00 |
| Comment: curb ramp replacement at 12 sf per ramp, 20 × 12 = 240 SF 5 curb ramps missing DWS = 5 × 12 = 60 |
| 536-1-1 | GUARDRAIL- ROADWAY, GEN TL-3 | 100.00 LF | 26.00 | 2,600.00 |
| Comment: Guardrail replacement at MP 35.643 RT |
| 536-8-112 | GUARDRA CONN TO RIGID BA, F&I, N APPR 3 | 1.00 EA | 3,300.00 | 3,300.00 |
| Comment: MP 35.643 RT |
| 536-73 | GUARDRAIL REMOVAL | 65.00 LF | 2.75 | 178.75 |
| Comment: Guardrail removal at MP 35.643 RT |
| 536-85-24 | GUARDRAIL END TREATMENT-PARA APP TERM | 1.00 EA | 3,500.00 | 3,500.00 |
| Comment: MP 35.643 RT |
| 570-1-2 | PERFORMANCE TURF, SOD | 90.00 SY | 6.25 | 562.50 |
| Comment: ADA curb ramp reconstruction |
| 710-11-123 | PAINTED PAVT MARK,STD,WHITE,SOLID, 12" | 2,298.00 LF | 1.75 | 4,021.50 |
| 710-11-125 | PAINTED PAVT MARK,STD,WHITE,SOLID,24" | 2,805.00 LF | 2.75 | 7,713.75 |
| 710-11-170 | PAINTED PAVT MARK,STD,WHITE, ARROWS | 61.00 EA | 45.00 | 2,745.00 |
C
===== PAGE 3 =====
| 710-11-201 | PAINTED PAVT MARK,STD,YELLOW,SOLID,6" | 7.15 GM | $1,585.00 | $11,332.75 |
| 711-11-123 | THERMOPLASTIC, STD, WHITE, SOLID, 12" | 2,298.00 LF | $4.00 | $9,192.00 |
| 711-11-125 | THERMOPLASTIC, STD, WHITE, SOLID, 24" | 2,805.00 LF | $7.75 | $21,738.75 |
| 711-11-170 | THERMOPLASTIC, STD, WHITE, ARROW | 61.00 EA | $95.00 | $5,795.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 706-1-3 | RAISED PAVMT MARK, TYPE B | 724.00 EA | $5.00 | $3,620.00 |
| 710-11-101 | PAINTED PAVT MARK,STD,WHITE,SOLID,6" | 7.15 GM | $1,585.00 | $11,332.75 |
| 710-11-131 | PAINTED PAVT MARK,STD,WHITE,SKIP, 6" | 3.58 GM | $700.00 | $2,506.00 |
| 711-16-101 | THERMOPLASTIC, STD-OTH, WHITE, SOLID, 6" | 7.15 GM | $5,550.00 | $39,682.50 |
| 711-16-131 | THERMOPLASTIC, STD-OTH, WHITE, SKIP, 6" | 3.58 GM | $1,800.00 | $6,444.00 |
| 711-16-201 | THERMOPLASTIC, STD-OTH,YELLOW, SOLID, 6" | 7.15 GM | $5,550.00 | $39,682.50 |
| Roadway Component Total | | | $2,199,520.31 |
| Total Width (T) / 8" Overlap (O) | T |
| Rumble Strips bar t 1/2No. of Sides | 0 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 327-70-6 | MILLING EXIST ASPH PAVT,1 1/2" AVG DEPTH | 8,391.68 SY | 3.75 | 31,468.80 |
| 337-7-83 | ASPH CONC FC,TRAFFIC C,FC-12.5,PG 76-22 | 692.31 TN | 169.25 | 117,173.47 |
| 570-1-2 | PERFORMANCE TURF, SOD | 5,601.45 SY | 6.25 | 35,009.06 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 160-4 | TYPE B STABILIZATION | 72.00 SY | 26.00 | 1,872.00 |
| Comment: Shoulder widening at SR 50 | | | |
| 285-701 | OPTIONAL BASE,BASE GROUP 01 | 34.00 SY | 37.50 | 1,275.00 |
| Comment: Shoulder widening at SR 50 | | | |
| 334-1-13 | SUPERPAVE ASPHALTIC CONC, TRAFFIC C | 2.79 TN | 319.00 | 890.01 |
| Comment: Shoulder widening at SR 50, 33.72 SY x 165/2000 = 2.79 TN | | | |
| 337-7-83 | ASPH CONC FC,TRAFFIC C,FC-12.5,PG 76-22 | 2.79 TN | 169.25 | 472.21 |
| Comment: Shoulder widening at SR 50, 33.72 SY x 165/2000 = 2.79 TN | | | |
| 570-1-2 | PERFORMANCE TURF, SOD | 1,171.00 SY | 6.25 | 7,318.75 |
| Comment: Shoulder widening at SR 50 (17 SY). 15% of shoulder rework (1.788*5280*0.15)*(10ft-2.67ft)/9= 1154 SY | | | |
| Erosion Control |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 104-10-3 | SEDIMENT BARRIER | 2,600.00 LF | 2.75 | 7,150.00 |
| 104-11 | FLOATING TURBIDITY BARRIER | 500.00 LF | 16.25 | 8,125.00 |
| 104-12 | STAKED TURBIDITY BARRIER-NYL REINF PVC | 250.00 LF | 10.00 | 2,500.00 |
| 104-18 | INLET PROTECTION SYSTEM | 50.00 EA | 189.00 | 9,450.00 |
| 107-1 | LITTER REMOVAL | 13.00 AC | 101.00 | 1,313.00 |
| 107-2 | MOWING | 13.00 AC | 121.00 | 1,573.00 |
| Shoulder Component Total | | | 225,590.30 |
| MEDIAN COMPONENT |
| User Input Data |
| Description | Value |
| Total Median Width | 40.00 |
| Performance Turf Width | 0.00 |
| Total Median Shoulder Width L/R | 0.00 / 0.00 |
| Paved Median Shoulder Width L/R | 0.00 / 0.00 |
| Structural Spread Rate | 110 |
| Friction Course Spread Rate | 80 |
| Total Width (T) / 8" Overlap (O) | T |
| Rumble Strips bar t 1/2No. of Sides | 0 |
## X-Items
===== PAGE 5 =====
| Pay items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 700-1-111 | SINGLE COL GRND SIGN AS, F&I GM, <12 SF | 36.00 EA | $572.00 | $20,592.00 |
| 700-1-112 | SINGLE COL GRND SIGN AS, F&I GM, 12-20 | 33.00 EA | $2,025.00 | $66,825.00 |
| 700-1-500 | SINGLE COL GRND SIGN AS, RELOCATE | 4.00 EA | $350.00 | $1,400.00 |
| 700-1-600 | SINGLE COL GRND SIGN AS, REMOVE | 29.00 EA | $50.00 | $1,450.00 |
| 700-2-114 | MULTI- COLUMN SIGN, F&I GM, 30.1-50 SF | 9.00 EA | $8,130.00 | $73,170.00 |
| 700-2-600 | MULTI- COLUMN GROUND SIGN, REMOVE | 1.00 EA | $1,260.00 | $1,260.00 |
| Signing Component Total | $164,697.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F& I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 6.00 EA | $1,722.00 | $10,332.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 2.00 EA | $2,955.00 | $5,910.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 2.00 AS | $1,015.00 | $2,030.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 5.00 AS | $1,945.00 | $9,725.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 2.00 EA | $422.00 | $844.00 |
===== PAGE 6 =====
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F& I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 10.00 EA | $1,722.00 | $17,220.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 6.00 EA | $2,955.00 | $17,730.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 6.00 AS | $1,015.00 | $6,090.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 3.00 AS | $1,945.00 | $5,835.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 6.00 EA | $422.00 | $2,532.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 646-1-60 | ALUMINUM SIGNALS POLE, REMOVE | 3.00 EA | $455.00 | $1,365.00 |
| 650-2-102 | VEHIC SIGNAL AUX, REP/RETROFIT- F&I, BAC | 7.00 EA | $600.00 | $4,200.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 4.00 AS | $1,545.00 | $6,180.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM- VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM- VIDEO, ABOVE G | 3.00 EA | $8,100.00 | $24,300.00 |
| 660-4-60 | VEHICLE DETECTION SYSTEM- VIDEO, REMOVE | 3.00 EA | $605.00 | $1,815.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS- VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS- VIDEO, F&I, ABO | 3.00 EA | $12,110.00 | $36,330.00 |
| 684-1-1 | MANAGED FIELD ETHERNET SWITCH, F&I | 1.00 EA | $5,425.00 | $5,425.00 |
| 685-1-13 | UPS, F&I, LINE INTERACTIVE W CAB | 1.00 EA | $13,815.00 | $13,815.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F& I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 8.00 EA | $1,722.00 | $13,776.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 8.00 EA | $2,955.00 | $23,640.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 8.00 AS | $1,015.00 | $8,120.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 6.00 AS | $1,945.00 | $11,670.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 8.00 EA | $422.00 | $3,376.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 646-1-60 | ALUMINUM SIGNALS POLE, REMOVE | 2.00 EA | $455.00 | $910.00 |
| 650-1-16 | VEH TRAF SIGNAL,F&I ALUMINUM, 4 S 1 W | 2.00 AS | $2,150.00 | $4,300.00 |
| 650-2-109 | VEHIC SIGNAL AUX, REP/RETR F&I, FLEX BAC | 8.00 EA | $710.00 | $5,680.00 |
| 653-1-60 | PEDESTRIAN SIGNAL, REMOVE | 2.00 AS | $130.00 | $260.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 4.00 AS | $1,545.00 | $6,180.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM-VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM-VIDEO, ABOVE G | 4.00 EA | $8,100.00 | $32,400.00 |
| 660-4-60 | VEHICLE DETECTION SYSTEM-VIDEO, REMOVE | 4.00 EA | $605.00 | $2,420.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, ABO | 4.00 EA | $12,110.00 | $48,440.00 |
| 665-1-60 | PEDESTRIAN DETECTOR, REMOVE | 2.00 EA | $70.00 | $140.00 |
| 684-1-1 | MANAGED FIELD ETHERNET SWITCH, F&I | 1.00 EA | $5,425.00 | $5,425.00 |
| 685-1-13 | UPS, F&I, LINE INTERACTIVE W CAB | 1.00 EA | $13,815.00 | $13,815.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 646-1-60 | ALUMINUM SIGNALS POLE, REMOVE | 2.00 EA | $455.00 | $910.00 |
| 650-2-109 | VEHIC SIGNAL AUX, REP/RETR F&I, FLEX BAC | 7.00 EA | $710.00 | $4,970.00 |
| 653-1-60 | PEDESTRIAN SIGNAL, REMOVE | 1.00 AS | $130.00 | $130.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 4.00 AS | $1,545.00 | $6,180.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM-VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM-VIDEO, ABOVE G | 3.00 EA | $8,100.00 | $24,300.00 |
| 660-4-60 | VEHICLE DETECTION SYSTEM-VIDEO, REMOVE | 3.00 EA | $605.00 | $1,815.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, ABO | 3.00 EA | $12,110.00 | $36,330.00 |
| 665-1-60 | PEDESTRIAN DETECTOR, REMOVE | 1.00 EA | $70.00 | $70.00 |
| 684-1-1 | MANAGED FIELD ETHERNET SWITCH, F&I | 1.00 EA | $5,425.00 | $5,425.00 |
| 685-1-13 | UPS, F&I, LINE INTERACTIVE W CAB | 1.00 EA | $13,815.00 | $13,815.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 110-1-1 | CLEARING & GRUBBING | 0.31 AC | 22,500.00 | 6,975.00 |
| Comment: Median modifications and sod removal |
| 110-4-10 | REMOVAL OF EXIST CONC | 789.00 SY | 46.00 | 36,294.00 |
| Comment: 10 curb ramps ADA in-kind(140 SY) & 25 curb ramps ADA recon with addtl drainage/sdwlk impacts(467 SY). Driveway apron removal at pelican pt(100 SY). Curb rmvl @ Harrison(28SY). Dwy rmvl 1.85(54SY) |
| 160-4 | TYPE B STABILIZATION | 127.00 SY | 26.00 | 3,302.00 |
| Comment: Asphalt reconstruction of existing driveway apron at Pelican Pt (100 SY). Median widening at Harrison (27 SY). |
| 285-701 | OPTIONAL BASE,BASE GROUP 01 | 100.00 SY | 37.50 | 3,750.00 |
| Comment: Asphalt reconstruction of existing driveway apron at Pelican Pt (100 SY). |
| 285-709 | OPTIONAL BASE,BASE GROUP 09 | 27.00 SY | 93.00 | 2,511.00 |
| Comment: Median widening at Harrison (27 SY). |
| 327-70-1 | MILLING EXIST ASPH PAVT, 1" AVG DEPTH | 1,835.00 SY | 4.25 | 7,798.75 |
| Comment: Deeper rehab for 5% of project, 36,692.48 × 0.05 = 1835 SY |
| 327-70-4 | MILLING EXIST ASPH PAVT, 3" AVG DEPTH | 7,016.00 SY | 3.25 | 22,802.00 |
| Comment: 28 Turn lanes × 11-ft (avg) × 205-ft (avg) = 7,016 SY |
| 334-1-53 | SUPERPAVE ASPH CONC, TRAF C, PG76-22 | 694.00 TN | 160.00 | 111,040.00 |
| Comment: 1" for deeper rehab for 5% (1835 × 110/2000 = 101 TN 1.5" for 28 turn lanes (7016 × 165/2000 = 579 TN) 1.5" for Pelican Pt (100SY × 165/2000 = 9TN) 3" for median widening at Harrison (26.2 ×330/2000) |
| 337-7-83 | ASPH CONC FC, TRAFFIC C,FC-12.5,PG 76-22 | 591.00 TN | 169.25 | 100,026.75 |
| Comment: 1.5" for 28 turn lanes (7016 × 165/2000 = 579 TN) 1.5" for Pelican Pt turnout (100SY × 165/2000 = 9TN) 3" for median widening at Harrison (26.2 ×165/2000 = 3 TN) |
===== PAGE 11 =====
| 520-1-10 | CONCRETE CURB & GUTTER, TYPE F | 1,175.00 LF | $52.25 | $61,393.75 |
| Comment: 35 curb ramps for ADA reconstruction (18LF per ramp= 630). 195LF for SB right turn lane at Harrison. 350LF for driveway removals at MP 1,850, MP 1,895, MP 2,350, 2,850. |
| 522-1 | CONCRETE SIDEWALK AND DRIVEWAYS, 4" | 256.00 SY | $86.00 | $22,016.00 |
| Comment: Sidewalk impacts for curb ramp reconstruction and driveway removal (218SY) and 38 SY for new connection on terrier trl |
| 522-2 | CONCRETE SIDEWALK AND DRIVEWAYS, 6" | 381.00 SY | $117.00 | $44,577.00 |
| Comment: 35 curb ramps for ADA reconstruction, 10 SY each. 31 SY for new crossing at terrier trl |
| 527-2 | DETECTABLE WARNINGS | 420.00 SF | $35.00 | $14,700.00 |
| Comment: 35 curb ramps for ADA reconstruction, 12 SF each |
| 570-1-2 | PERFORMANCE TURF, SOD | 312.00 SY | $6.25 | $1,950.00 |
| Comment: curb ramp reconstruction. 136 SY for SB Right turn lane at Harrison St. |
| 710-11-123 | PAINTED PAVT MARK,STD,WHITE,SOLID, 12" | 3,680.00 LF | $1.75 | $6,440.00 |
| 710-11-125 | PAINTED PAVT MARK,STD,WHITE,SOLID,24" | 3,372.00 LF | $2.75 | $9,273.00 |
| 710-11-170 | PAINTED PAVT MARK,STD,WHITE, ARROWS | 56.00 EA | $45.00 | $2,520.00 |
| 710-11-201 | PAINTED PAVT MARK,STD,YELLOW,SOLID,6" | 5.21 GM | $1,585.00 | $8,257.85 |
| 711-11-123 | THERMOPLASTIC, STD, WHITE, SOLID, 12" | 3,680.00 LF | $4.00 | $14,720.00 |
| 711-11-125 | THERMOPLASTIC, STD, WHITE, SOLID, 24" | 3,372.00 LF | $7.75 | $26,133.00 |
| 711-11-170 | THERMOPLASTIC, STD, WHITE, ARROW | 56.00 EA | $95.00 | $5,320.00 |
| Turnouts/Crossovers Subcomponent |
| Description | Value |
| Asphalt Adjustment | 5.00 |
| Milling Code | Y |
| Friction Course Code | Y |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 327-70-4 | MILLING EXIST ASPH PAVT, 3" AVG DEPTH | 1,834.62 SY | $3.25 | $5,962.52 |
| 334-1-53 | SUPERPAVE ASPH CONC, TRAF C, PG76-22 | 151.36 TN | $160.00 | $24,217.60 |
| 337-7-83 | ASPH CONC FC,TRAFFIC C,FC-12.5,PG 76-22 | 151.36 TN | $169.25 | $25,617.68 |
| Pavement Marking Subcomponent |
| Description | Value |
| Include Thermo/Tape/Other | Y |
| Pavement Type | Asphalt |
| Solid Stripe No. of Paint Applications | 1 |
| Solid Stripe No. of Stripes | 4 |
| Skip Stripe No. of Paint Applications | 1 |
| Skip Stripe No. of Stripes | 2 |
===== PAGE 12 =====
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 706-1-3 | RAISED PAVMT MARK, TYPE B PAINTED PAVT MARK,STD,WHITE,SOLID,6" | 528.00 EA | $5.00 | $2,640.00 |
| 710-11-101 | PAINTED PAVT MARK,STD,WHITE,SKIP, 6" | 5.21 GM | $1,585.00 | $8,257.85 |
| 710-11-131 | PAINTED PAVT MARK,STD,WHITE,SKIP, 6" | 2.61 GM | $700.00 | $1,827.00 |
| 711-16-101 | THERMOPLASTIC, STD-OTH, WHITE, SOLID, 6" | 5.21 GM | $5,550.00 | $28,915.50 |
| 711-16-131 | THERMOPLASTIC, STD-OTH, WHITE, SKIP, 6" | 2.61 GM | $1,800.00 | $4,698.00 |
| 711-16-201 | THERMOPLASTIC, STD-OTH, YELLOW, SOLID, 6" | 5.21 GM | $5,550.00 | $28,915.50 |
| Roadway Component Total | $1,758,784.86 |
| User Input Data |
| Description | Value |
| Total Outside Shoulder Width L/R | 10.00 / 10.00 |
| Total Outside Shoulder Perf. Turf Width L/R | 0.00 / 0.00 |
| Paved Outside Shoulder Width L/R | 8.00 / 8.00 |
| Structural Spread Rate | 165 |
| Friction Course Spread Rate | 165 |
| Total Width (T) / 8" Overlap (O) | T |
| Rumble Strips $ \frac{1}{2} $No. of Sides | 0 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 327-70-4 | MILLING EXIST ASPH PAVT, 3" AVG DEPTH | 12,230.83 SY | 3.25 | 39,750.20 |
| 334-1-53 | SUPERPAVE ASPH CONC, TRAF C, PG76-22 | 1,009.04 TN | 160.00 | 161,446.40 |
| 337-7-83 | ASPH CONC FC,TRAFFIC C,FC-12.5,PG 76-22 | 1,009.04 TN | 169.25 | 170,780.02 |
| Erosion Control |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 104-10-3 | SEDIMENT BARRIER | 920.00 LF | 2.75 | 2,530.00 |
| 104-11 | FLOATING TURBIDITY BARRIER | 200.00 LF | 16.25 | 3,250.00 |
| 104-12 | STAKED TURBIDITY BARRIER-NYL REINF PVC | 200.00 LF | 10.00 | 2,000.00 |
| 104-18 | INLET PROTECTION SYSTEM | 50.00 EA | 189.00 | 9,450.00 |
| 107-1 | LITTER REMOVAL | 9.47 AC | 101.00 | 956.47 |
| 107-2 | MOWING | 9.47 AC | 121.00 | 1,145.87 |
| Shoulder Component Total | 391,308.96 |
| A-items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 425-1-331 | INLETS, CURB, TYPE P-3, <10' | 2.00 EA | $11,650.00 | $23,300.00 |
| 425-1-341 | INLETS, CURB, TYPE P-4, <10' | 1.00 EA | $11,825.00 | $11,825.00 |
| 425-1-351 | INLETS, CURB, TYPE P-5, <10' | 1.00 EA | $10,200.00 | $10,200.00 |
| 425-1-441 | INLETS, CURB, TYPE J-4, <10' | 2.00 EA | $17,200.00 | $34,400.00 |
| 425-2-43 | MANHOLES, P-7, PARTIAL | 3.00 EA | $6,000.00 | $18,000.00 |
| 425-2-71 | MANHOLES, J-7, <10' | 1.00 EA | $13,500.00 | $13,500.00 |
| 425-5 | MANHOLE, ADJUST | 3.00 EA | $1,365.00 | $4,095.00 |
| 425-11 | MODIFY EXISTING DRAINAGE STRUCTURE | 1.00 EA | $4,420.00 | $4,420.00 |
| 430-175-118 | PIPE CULV, OPT MATL, ROUND, 18"S/CD | 232.00 LF | $201.75 | $46,806.00 |
| Drainage Component Total | | | $166,546.00 |
| Pay items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 700-1-111 | SINGLE COL GRND SIGN AS, F&I GM, <12 SF | 27.00 EA | $572.00 | $15,444.00 |
| 700-1-112 | SINGLE COL GRND SIGN AS, F&I GM, 12-20 | 24.00 EA | $2,025.00 | $48,600.00 |
| 700-1-500 | SINGLE COL GRND SIGN AS, RELOCATE | 3.00 EA | $350.00 | $1,050.00 |
| 700-1-600 | SINGLE COL GRND SIGN AS, REMOVE | 21.00 EA | $50.00 | $1,050.00 |
| 700-2-114 | MULTI- COLUMN SIGN, F&I GM, 30.1-50 SF | 9.00 EA | $8,130.00 | $73,170.00 |
| 700-2-600 | MULTI- COLUMN GROUND SIGN, REMOVE | 1.00 EA | $1,260.00 | $1,260.00 |
| Signing Component Total | $140,574.00 |
## SIGNALIZATIONS COMPONENT
===== PAGE 14 =====
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F& I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 16.00 EA | $1,722.00 | $27,552.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 6.00 EA | $2,955.00 | $17,730.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 6.00 AS | $1,015.00 | $6,090.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 3.00 AS | $1,945.00 | $5,835.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 6.00 EA | $422.00 | $2,532.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 646-1-60 | ALUMINUM SIGNALS POLE, REMOVE | 3.00 EA | $455.00 | $1,365.00 |
| 650-2-109 | VEHIC SIGNAL AUX, REP/RETR F&I, FLEX BAC | 6.00 EA | $710.00 | $4,260.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 4.00 AS | $1,545.00 | $6,180.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM-VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM-VIDEO, ABOVE G | 3.00 EA | $8,100.00 | $24,300.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, ABO | 3.00 EA | $12,110.00 | $36,330.00 |
| 684-1-1 | MANAGED FIELD ETHERNET SWITCH, F&I | 1.00 EA | $5,425.00 | $5,425.00 |
| 685-1-13 | UPS, F&I, LINE INTERACTIVE W CAB | 1.00 EA | $13,815.00 | $13,815.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 8.00 EA | $2,955.00 | $23,640.00 |
| 650-1-14 | VEH TRAF SIGNAL,F&I ALUMINUM, 3 S 1 W | 8.00 AS | $1,780.00 | $14,240.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 8.00 AS | $1,015.00 | $8,120.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 5.00 AS | $1,945.00 | $9,725.00 |
| 665-1-12 | PEDESTRIAN DETECTOR, F&I, ACCESSIBLE | 8.00 EA | $1,645.00 | $13,160.00 |
| 700-5-21 | INTERNAL ILLUM SIGN, F&I OM, UP TO 12 SF | 4.00 EA | $4,720.00 | $18,880.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 633-1-122 | FIBER OPTIC CABLE, F&I, UG, 13-48 | 200.00 LF | $5.00 | $1,000.00 |
| 633-2-32 | FIBER OPTIC CONNECTION, INSTALL, TERM | 12.00 EA | $90.00 | $1,080.00 |
| 633-3-11 | FIBER OPTIC CONN HDWR, SPLICE ENCLOSURE | 1.00 EA | $1,505.00 | $1,505.00 |
| 633-3-14 | FIBER OPTIC CONN HDWR, BUFFER TUBE FAN O | 1.00 EA | $100.00 | $100.00 |
| 633-3-16 | FIBER OPTIC CONN HDWR, PATCH PANEL- FIE | 1.00 EA | $1,425.00 | $1,425.00 |
| 635-2-13 | PULL & SPLICE BOX, F&I, 30" X 60" OR 36" | 1.00 EA | $6,175.00 | $6,175.00 |
| 639-1-122 | ELECTRICAL POWER SRV, F&I, UG, PUR CONT | 1.00 AS | $5,400.00 | $5,400.00 |
| 639-1-610 | ELECTRICAL POWER SRV, REMOHD | 1.00 AS | $930.00 | $930.00 |
| 641-2-12 | PREST CNC POLE, F&I, TYP P-II SRV POLE | 1.00 EA | $2,505.00 | $2,505.00 |
| 641-2-80 | PREST CNC POLE, REMOVE COMPLETE | 4.00 EA | $10,000.00 | $40,000.00 |
| 649-21-13 | STEEL MAST ARM ASSEMBLY, F&I, 60'- 50' | 1.00 EA | $95,000.00 | $95,000.00 |
| 649-21-18 | STEEL MAST ARM ASSEMBLY, F&I, 70'- 50' | 1.00 EA | $125,600.00 | $125,600.00 |
| 650-1-16 | VEH TRAF SIGNAL, F&I ALUMINUM, 4 S 1 W | 2.00 AS | $2,150.00 | $4,300.00 |
| 660-1-109 | LOOP DETECTOR INDUCTIVE, F&I, TYPE 9 | 4.00 EA | $420.00 | $1,680.00 |
| 660-1-110 | LOOP DETECTOR INDUCTIVE, F&I, TYPE 10 | 1.00 EA | $515.00 | $515.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 4.00 AS | $1,545.00 | $6,180.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM- VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM- VIDEO, ABOVE G | 4.00 EA | $8,100.00 | $32,400.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS- VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS- VIDEO, F&I, ABO | 4.00 EA | $12,110.00 | $48,440.00 |
| 663-1-111 | SIGNAL PRIO & PREEMP, F&I, OPT, CAB E | 1.00 EA | $9,200.00 | $9,200.00 |
| 663-1-112 | SIGNAL PRIO & PREEMP, F&I, OPTICAL, DETEC | 4.00 EA | $2,515.00 | $10,060.00 |
| 670-5-112 | TRAFF CNTL ASSEM, F&I, NEMA, 2 PREEMPT | 1.00 AS | $55,000.00 | $55,000.00 |
| 670-5-600 | TRAFF CNTL ASSEM, REMOVE | 1.00 AS | $985.00 | $985.00 |
===== PAGE 16 =====
| Pay Item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F& I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 10.00 EA | $1,722.00 | $17,220.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 6.00 EA | $2,955.00 | $17,730.00 |
| 650-1-14 | VEH TRAF SIGNAL,F&I ALUMINUM, 3 S 1 W | 1.00 AS | $1,780.00 | $1,780.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 6.00 AS | $1,015.00 | $6,090.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 5.00 AS | $1,945.00 | $9,725.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 6.00 EA | $422.00 | $2,532.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 650-1-16 | VEH TRAF SIGNAL, F&I ALUMINUM, 4 S 1 W | 2.00 AS | $2,150.00 | $4,300.00 |
| 650-1-60 | VEH TRAF SIGNAL, REMOVE POLES TO REMAIN | 1.00 AS | $300.00 | $300.00 |
| 650-2-109 | VEHIC SIGNAL AUX, REP/RETR F&I, FLEX BAC | 6.00 EA | $710.00 | $4,260.00 |
| 653-1-60 | PEDESTRIAN SIGNAL, REMOVE | 4.00 AS | $130.00 | $520.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 4.00 AS | $1,545.00 | $6,180.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM-VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM-VIDEO, ABOVE G | 4.00 EA | $8,100.00 | $32,400.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, ABO | 4.00 EA | $12,110.00 | $48,440.00 |
| 665-1-60 | PEDESTRIAN DETECTOR, REMOVE | 4.00 EA | $70.00 | $280.00 |
| 684-1-1 | MANAGED FIELD ETHERNET SWITCH, F&I | 1.00 EA | $5,425.00 | $5,425.00 |
| 685-1-13 | UPS, F&I, LINE INTERACTIVE W CAB | 1.00 EA | $13,815.00 | $13,815.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F& I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 10.00 EA | $1,722.00 | $17,220.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 8.00 EA | $2,955.00 | $23,640.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 8.00 AS | $1,015.00 | $8,120.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 3.00 AS | $1,945.00 | $5,835.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 8.00 EA | $422.00 | $3,376.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 646-1-60 | ALUMINUM SIGNALS POLE, REMOVE | 7.00 EA | $455.00 | $3,185.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 2.00 AS | $1,545.00 | $3,090.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM-VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM-VIDEO, ABOVE G | 4.00 EA | $8,100.00 | $32,400.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, ABO | 4.00 EA | $12,110.00 | $48,440.00 |
| 682-1-113 | ITS CCTV CAMERA, F&I, DOME ENCL-PRESS | 1.00 EA | $8,365.00 | $8,365.00 |
| 684-1-1 | MANAGED FIELD ETHERNET SWITCH, F&I | 1.00 EA | $5,425.00 | $5,425.00 |
| 685-1-13 | UPS, F&I, LINE INTERACTIVE W CAB | 1.00 EA | $13,815.00 | $13,815.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| Traffic Monitoring 1 |
| Description | Value |
| Lanes | 4 |
| Multiplier | 1 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 695-1-1 | TMS VEH SNSR-NON-WEIGHT, F&I, | 4.00 EA | $2,750.00 | $11,000.00 |
| 695-6-12 | TMS IND LOOP ASSEMBLY | 4.00 EA | $2,175.00 | $8,700.00 |
| Signalizations Component Total | $1,417,762.00 |
## LIGHTING COMPONENT
| Spacing\nPay Items\nPay item | Description | Quantity Unit | Unit Price | MIN |
| $23.25 | Extended Amount |
| 630-2-11 | CONDUIT, F& I, OPEN TRENCH | 2,200.00 LF | $23.25 | 51,150.00 < /td > < /tr > < tr > < td style = 'text-align: center; word-wrap: break-word;' > 630-2-12 < /td > < td style = 'text-align: center; word-wrap: break-word;' > CONDUIT, F amp; I, DIRECTIONALnBORE < /td > < td style = 'text-align: center; word-wrap: break-word;' > 1,600.00 LF < /td > < td style = 'text-align: center; word-wrap: break-word;' >40.00 | 64,000.00 < /td > < /tr > < tr > < td style = 'text-align: center; word-wrap: break-word;' > 635-2-11 < /td > < td style = 'text-align: center; word-wrap: break-word;' > PULL amp; SPLICE BOX, F amp;I, 13 quot; xn24 quot; < /td > < td style = 'text-align: center; word-wrap: break-word;' > 56.00 EA < /td > < td style = 'text-align: center; word-wrap: break-word;' >1,722.00 | 96,432.00 < /td > < /tr > < tr > < td style = 'text-align: center; word-wrap: break-word;' > 715-61-342 < /td > < td style = 'text-align: center; word-wrap: break-word;' > LIGHT POLE CMPLT,STD,F amp;I,n40 #x27;MH,12 #x27;ARM L < /td > < td style = 'text-align: center; word-wrap: break-word;' > 32.00 EA < /td > < td style = 'text-align: center; word-wrap: break-word;' >10,600.00 | 339,200.00 < /td > < /tr > < tr > < td style = 'text-align: center; word-wrap: break-word;' > 715-500-1 < /td > < td style = 'text-align: center; word-wrap: break-word;' > POLE CABLE DIST SYS,nCONVENTIONALnSubcomponent Total < /td > < td style = 'text-align: center; word-wrap: break-word;' > 32.00 EA < /td > < td style = 'text-align: center; word-wrap: break-word;' >930.00 | 29,760.00n580,542.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 715-1-12 | LIGHTING CONDUCTORS, F&I,\nINSUL,NO.8-6 | 11,400.00 LF | $3.25 | $37,050.00 |
| 715-7-11 | LOAD CENTER, F&I, SECONDARY\nVOLTAGE | 4.00 EA | $22,210.00 | $88,840.00 |
| 715-68-000 | LIGHT POLE COMPLETE,\nRELOCATE | 1.00 EA | $7,000.00 | $7,000.00 |
| Lighting Component Total | $713,432.00 |
| Sequence 2 Total | $4,595,168.07 |
===== PAGE 19 =====
Description: SR 5 (US 1) from Grace St to SR 405/Garden St (MP 3.078 to MP 4.090) Northbound only. Includes intersection lighting retrofit for 3 signals and 2 poles for midblock crossings.
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 110-1-1 | CLEARING & GRUBBING | 0.03 AC | $22,500.00 | $675.00 |
| Comment: Sod removal for curb ramp work | | | |
| 110-4-10 | REMOVAL OF EXIST CONC | 267.00 SY | $46.00 | $12,282.00 |
| Comment: 20 curb ramps for ADA reconstruction | | | |
| 327-70-1 | MILLING EXIST ASPH PAVT, 1" AVG DEPTH | 654.00 SY | $4.25 | $2,779.50 |
| Comment: Deeper rehab for 5% of project (13,061.55 * 0.05 = 654 SY) | | | |
| 327-70-4 | MILLING EXIST ASPH PAVT, 3" AVG DEPTH | 2,107.00 SY | $3.25 | $6,847.75 |
| Comment: 7 turn lanes, approx. 10-ft wide x 185ft long (avg) = 1439 SY South St milling between NB and SB legs, 668 SY | | | |
| 334-1-13 | SUPERPAVE ASPHALTIC CONC, TRAFFIC C | 211.00 TN | $319.00 | $67,309.00 |
| Comment: 1" for deeper rehab for 5% of project = 654 * 110/2000 = 36 TN 1.5" lift for 7 turn lanes = 1439 * 165/2000 = 119 TN 1.5" lift for South St = 668 *165/2000 = 56 TN | | | |
| 337-7-83 | ASPH CONC FC,TRAFFIC C,FC-12.5,PG 76-22 | 175.00 TN | $169.25 | $29,618.75 |
| Comment: 1.5" for 7 turn lanes = 1439 * 165/2000 = 119 TN 1.5" for South St = 668 *165/2000 = 56 TN | | | |
| 520-1-10 | CONCRETE CURB & GUTTER, TYPE F | 300.00 LF | $52.25 | $15,675.00 |
| Comment: 20 curb ramps for ADA reconstruction | | | |
| 522-1 | CONCRETE SIDEWALK AND DRIVEWAYS, 4" | 84.00 SY | $86.00 | $7,224.00 |
| Comment: Sidewalk impacts for curb ramp reconstruction | | | |
| 522-2 | CONCRETE SIDEWALK AND DRIVEWAYS, 6" | 200.00 SY | $117.00 | $23,400.00 |
| Comment: 20 curb ramps for ADA reconstruction, 10 SY each | | | |
| 527-2 | DETECTABLE WARNINGS | 240.00 SF | $35.00 | $8,400.00 |
| Comment: 20 curb ramp reconstructions at 12 SF each | | | |
===== PAGE 20 =====
| 570-1-2 | PERFORMANCE TURF, SOD\nComment: 20 curb ramps for ADA reconstruction | 91.00 SY | $6.25 | $568.75 |
| 710-11-123 | PAINTED PAVT\nMARK,STD,WHITE,SOLID, 12" | 1,692.00 LF | $1.75 | $2,961.00 |
| 710-11-125 | PAINTED PAVT\nMARK,STD,WHITE,SOLID,24" | 2,256.00 LF | $2.75 | $6,204.00 |
| 710-11-170 | PAINTED PAVT MARK,STD,WHITE, ARROWS | 22.00 EA | $45.00 | $990.00 |
| 710-11-201 | PAINTED PAVT MARK,STD,YELLOW,SOLID,6" | 2.02 GM | $1,585.00 | $3,201.70 |
| 711-11-123 | THERMOPLASTIC, STD, WHITE, SOLID, 12" | 1,692.00 LF | $4.00 | $6,768.00 |
| 711-11-125 | THERMOPLASTIC, STD, WHITE, SOLID, 24" | 2,256.00 LF | $7.75 | $17,484.00 |
| 711-11-170 | THERMOPLASTIC, STD, WHITE, ARROW | 22.00 EA | $95.00 | $2,090.00 |
| Pavement Marking Subcomponent |
| Description | Value |
| Include Thermo/Tape/Other | Y |
| Pavement Type | Asphalt |
| Solid Stripe No. of Paint Applications | 1 |
| Solid Stripe No. of Stripes | 2 |
| Skip Stripe No. of Paint Applications | 1 |
| Skip Stripe No. of Stripes | 1 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 706-1-3 | RAISED PAVMT MARK, TYPE B | 137.00 EA | $5.00 | $685.00 |
| 710-11-101 | PAINTED PAVT\nMARK,STD,WHITE,SOLID,6" | 2.02 GM | $1,585.00 | $3,201.70 |
| 710-11-231 | PAINTED PAVT\nMARK,STD,YELLOW,SKIP,6" | 1.01 GM | $676.00 | $682.76 |
| 711-16-101 | THERMOPLASTIC, STD-OTH, WHITE, SOLID, 6" | 2.02 GM | $5,550.00 | $11,211.00 |
| 711-16-201 | THERMOPLASTIC, STD-OTH,YELLOW, SOLID, 6" | 2.02 GM | $5,550.00 | $11,211.00 |
| 711-16-231 | THERMOPLASTIC, STD-OTH, YELLOW, SKIP, 6" | 1.01 GM | $1,800.00 | $1,818.00 |
| Roadway Component Total | $640,531.17 |
| 334-1-13 | Comment: On-street parking, 8-ft wide × 1,120ft / 9 = 996\nSY |
| SUPERPAVE ASPHALTIC CONC, TRAFFIC C | 83.00 TN | 319.00 | 26,477.00 |
| Comment: 1.5" lift for on-street parking, 996 *165 /2000 = 83 TN |
| 337-7-83 | ASPH CONC FC,TRAFFIC C,FC-12.5,PG 76-22 | 83.00 TN | 169.25 | 14,047.75 |
| Comment: 1.5" lift for on-street parking, 996 *165 /2000 = 83 TN |
| Erosion Control |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 104-10-3 | SEDIMENT BARRIER | 175.00 LF | 2.75 | 481.25 |
| 104-12 | STAKED TURBIDITY BARRIER-NYL REINF PVC | 125.00 LF | 10.00 | 1,250.00 |
| 104-18 | INLET PROTECTION SYSTEM | 20.00 EA | 189.00 | 3,780.00 |
| 107-1 | LITTER REMOVAL | 2.45 AC | 101.00 | 247.45 |
| 107-2 | MOWING | 2.45 AC | 121.00 | 296.45 |
| Shoulder Component Total | 49,816.90 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 700-1-111 | SINGLE COL GRND SIGN AS, F&I GM, <12 SF | 11.00 EA | $572.00 | $6,292.00 |
| 700-1-112 | SINGLE COL GRND SIGN AS, F&I GM, 12-20 | 15.00 EA | $2,025.00 | $30,375.00 |
| 700-1-500 | SINGLE COL GRND SIGN AS, RELOCATE | 3.00 EA | $350.00 | $1,050.00 |
| 700-1-600 | SINGLE COL GRND SIGN AS, REMOVE | 13.00 EA | $50.00 | $650.00 |
| 700-2-114 | MULTI- COLUMN SIGN, F&I GM, 30.1-50 SF | 6.00 EA | $8,130.00 | $48,780.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 700-3-202 | SIGN PANEL, F&I OM, 12-20 SF | 7.00 EA | $1,385.00 | $9,695.00 |
| 700-3-602 | SIGN PANEL, REMOVE, 12-20 SF | 7.00 EA | $71.50 | $500.50 |
| Comment: overhead sign structure at MP 4.048 |
| Signing Component Total | $97,342.50 |
===== PAGE 22 =====
## SIGNALIZATIONS COMPONENT
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F& I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 10.00 EA | $1,722.00 | $17,220.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 8.00 EA | $2,955.00 | $23,640.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 8.00 AS | $1,015.00 | $8,120.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 3.00 AS | $1,945.00 | $5,835.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 8.00 EA | $422.00 | $3,376.00 |
| 700-5-21 | INTERNAL ILLUM SIGN, F&I OM, UP TO 12 SF | 2.00 EA | $4,720.00 | $9,440.00 |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 646-1-60 | ALUMINUM SIGNALS POLE, REMOVE | 4.00 EA | $455.00 | $1,820.00 |
| 650-2-109 | VEHIC SIGNAL AUX, REP/RETR F&I, FLEX BAC | 6.00 EA | $710.00 | $4,260.00 |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 2.00 AS | $1,545.00 | $3,090.00 |
| 660-4-11 | VEHICLE DETECTION SYSTEM-VIDEO, CABINET | 1.00 EA | $21,000.00 | $21,000.00 |
| 660-4-12 | VEHICLE DETECTION SYSTEM-VIDEO, ABOVE G | 3.00 EA | $8,100.00 | $24,300.00 |
| 660-9-11 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, CAB | 1.00 EA | $26,625.00 | $26,625.00 |
| 660-9-12 | TRAFFIC DATA DETECT SYS-VIDEO, F&I, ABO | 3.00 EA | $12,110.00 | $36,330.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 8.00 AS | $1,015.00 | $8,120.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 8.00 EA | $422.00 | $3,376.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 646-1-60 | ALUMINUM SIGNALS POLE, REMOVE | 4.00 EA | $455.00 | $1,820.00 |
| 650-2-109 | VEHIC SIGNAL AUX, REP/RETR F&I, FLEX BAC | 4.00 EA | $710.00 | $2,840.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| Signalization 3 |
| Description | Value |
| Type | 4 Lane Mast Arm |
| Multiplier | 1 |
| Description | SR 406/Garden St intersection |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-12 | CONDUIT, F&I, DIRECTIONAL BORE | 250.00 LF | $40.00 | $10,000.00 |
| 632-7-1 | SIGNAL CABLE- NEW OR RECO, FUR & INSTALL | 1.00 PI | $12,000.00 | $12,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 10.00 EA | $1,722.00 | $17,220.00 |
| 646-1-11 | ALUMINUM SIGNALS POLE, PEDESTAL | 8.00 EA | $2,955.00 | $23,640.00 |
| 653-1-11 | PEDESTRIAN SIGNAL, F&I LED COUNT, 1 WAY | 8.00 AS | $1,015.00 | $8,120.00 |
| 660-2-106 | LOOP ASSEMBLY, F&I, TYPE F | 5.00 AS | $1,945.00 | $9,725.00 |
| 665-1-11 | PEDESTRIAN DETECTOR, F&I, STANDARD | 8.00 EA | $422.00 | $3,376.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 660-2-102 | LOOP ASSEMBLY, F&I, TYPE B | 2.00 AS | $1,545.00 | $3,090.00 |
| 682-1-113 | ITS CCTV CAMERA, F&I, DOME ENCL-PRESS | 1.00 EA | $8,365.00 | $8,365.00 |
| 684-1-1 | MANAGED FIELD ETHERNET SWITCH, F&I | 1.00 EA | $5,425.00 | $5,425.00 |
| 685-1-13 | UPS, F&I, LINE INTERACTIVE W CAB | 1.00 EA | $13,815.00 | $13,815.00 |
| 685-2-1 | REMOTE POWER MANAGEMENT UNIT- RPMU, F&I | 1.00 EA | $1,260.00 | $1,260.00 |
| Traffic Monitoring 1 |
| Description | Value |
| Lanes | 2 |
| Multiplier | 1 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 695-1-1 | TMS VEH SNSR-NON-WEIGHT, F&I, | 2.00 EA | $2,750.00 | $5,500.00 |
| 695-6-12 | TMS IND LOOP ASSEMBLY | 2.00 EA | $2,175.00 | $4,350.00 |
===== PAGE 24 =====
| Traffic Monitoring 2 |
| Description | Value |
| Lanes | 2 |
| Multiplier | 1 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 695-1-1 | TMS VEH SNSR-NON-WEIGHT, F&I, | 2.00 EA | $2,750.00 | $5,500.00 |
| 695-6-12 | TMS IND LOOP ASSEMBLY | 2.00 EA | $2,175.00 | $4,350.00 |
| Traffic Monitoring 3 |
| Description | Value |
| Lanes | 2 |
| Multiplier | 1 |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 695-1-1 | TMS VEH SNSR-NON-WEIGHT, F&I, | 2.00 EA | $2,750.00 | $5,500.00 |
| 695-6-12 | TMS IND LOOP ASSEMBLY | 2.00 EA | $2,175.00 | $4,350.00 |
| Signalizations Component Total | $430,734.00 |
| LIGHTING COMPONENT |
| Conventional Lighting Subcomponent |
| Description | Value |
| Spacing | MAX |
| Pay Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 630-2-11 | CONDUIT, F&I, OPEN TRENCH | 1,700.00 LF | $23.25 | $39,525.00 |
| 630-2-12 | CONDUIT, F&I, DIRECTIONAL BORE | 1,300.00 LF | $40.00 | $52,000.00 |
| 635-2-11 | PULL & SPLICE BOX, F&I, 13" x 24" | 44.00 EA | $1,722.00 | $75,768.00 |
| 715-61-342 | LIGHT POLE CMPLT,STD,F&I, 40"MH,12"ARM L | 26.00 EA | $10,600.00 | $275,600.00 |
| 715-500-1 | POLE CABLE DIST SYS, CONVENTIONAL Subcomponent Total | 26.00 EA | $930.00 | $24,180.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 715-1-12 | LIGHTING CONDUCTORS, F&I, INSUL,NO.8-6 | 9,000.00 LF | $3.25 | $29,250.00 |
| 715-7-11 | LOAD CENTER, F&I, SECONDARY VOLTAGE | 3.00 EA | $22,210.00 | $66,630.00 |
| Lighting Component Total | $562,953.00 |
| X-Items |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 110-1-1 | CLEARING & GRUBBING | 0.11 AC | 22,500.00 | 2,475.00 |
| Comment: To fill sidewalk gap on Brevard St | | | |
| 110-4-10 | REMOVAL OF EXIST CONC | 14.00 SY | 46.00 | 644.00 |
| Comment: To fill sidewalk gap on Brevard St | | | |
| 327-70-4 | MILLING EXIST ASPH PAVT, 3" AVG DEPTH | 4,744.00 SY | 3.25 | 15,418.00 |
| Comment: Milling side streets | | | |
| 334-1-53 | SUPERPAVE ASPH CONC, TRAF C, PG76-22 | 392.00 TN | 160.00 | 62,720.00 |
| Comment: 1.5" for side streets, 4744 × 165/2000 = 392 TN | | | |
| 337-7-83 | ASPH CONC FC,TRAFFIC C,FC-12.5,PG 76-22 | 392.00 TN | 169.25 | 66,346.00 |
| Comment: 1.5" for side streets, 4744 × 165/2000 = 392 TN | | | |
| 520-1-10 | CONCRETE CURB & GUTTER, TYPE F | 65.00 LF | 52.25 | 3,396.25 |
| Comment: To fill sidewalk gap on Brevard St | | | |
| 522-1 | CONCRETE SIDEWALK AND DRIVEWAYS, 4" | 58.00 SY | 86.00 | 4,988.00 |
| Comment: To fill sidewalk gap on Brevard St | | | |
| 523-3 | PATTERNED PAVEMENT | 264.00 SY | 150.50 | 39,732.00 |
| Comment: For patterned crosswalks | | | |
| 710-11-101 | PAINTED PAVT MARK,STD,WHITE,SOLID,6" | 0.19 GM | 1,585.00 | 301.15 |
| 710-11-123 | PAINTED PAVT MARK,STD,WHITE,SOLID, 12" | 200.00 LF | 1.75 | 350.00 |
| 710-11-125 | PAINTED PAVT MARK,STD,WHITE,SOLID,24" | 211.00 LF | 2.75 | 580.25 |
| 710-11-170 | PAINTED PAVT MARK,STD,WHITE, ARROWS | 1.00 EA | 45.00 | 45.00 |
| 710-11-201 | PAINTED PAVT MARK,STD,YELLOW,SOLID,6" | 0.19 GM | 1,585.00 | 301.15 |
| 711-11-123 | THERMOPLASTIC, STD, WHITE, SOLID, 12" | 200.00 LF | 4.00 | 800.00 |
| 711-11-125 | THERMOPLASTIC, STD, WHITE, SOLID, 24" | 211.00 LF | 7.75 | 1,635.25 |
| 711-11-170 | THERMOPLASTIC, STD, WHITE, ARROW | 1.00 EA | 95.00 | 95.00 |
| 711-16-101 | THERMOPLASTIC, STD-OTH, WHITE, SOLID, 6" | 0.19 GM | 5,550.00 | 1,054.50 |
| 711-16-201 | THERMOPLASTIC, STD-OTH,YELLOW, SOLID, 6" | 0.19 GM | 5,550.00 | 1,054.50 |
| 714-10 | GREEN-COLORED PAVEMENT MARKINGS, BIKE LN | 1,652.00 SF | 11.00 | 18,172.00 |
| Comment: For green bike lane | | | |
| Roadway Component Total | | | 220,108.05 |
===== PAGE 27 =====
| A Name | Description | Quantity Unit | Unit Price | Extended Amount |
| Pay item | Description | Quantity Unit | Unit Price | Extended Amount |
| 425-1-311 | INLETS, CURB, TYPE P-1, <10' | 1.00 EA | $12,000.00 | $12,000.00 |
| 425-1-331 | INLETS, CURB, TYPE P-3, <10' | 1.00 EA | $11,650.00 | $11,650.00 |
| 425-1-351 | INLETS, CURB, TYPE P-5, <10' | 1.00 EA | $10,200.00 | $10,200.00 |
| 425-1-361 | INLETS, CURB, TYPE P-6, <10' | 4.00 EA | $11,000.00 | $44,000.00 |
| 425-1-521 | INLETS, DT BOT, TYPE C, <10' | 2.00 EA | $8,000.00 | $16,000.00 |
| 425-2-41 | MANHOLES, P-7, <10' | 2.00 EA | $9,000.00 | $18,000.00 |
| 425-2-43 | MANHOLES, P-7, PARTIAL | 3.00 EA | $6,000.00 | $18,000.00 |
| 425-5 | MANHOLE, ADJUST | 1.00 EA | $1,365.00 | $1,365.00 |
| 425-11 | MODIFY EXISTING DRAINAGE STRUCTURE | 2.00 EA | $4,420.00 | $8,840.00 |
| 430-175-118 | PIPE CULV, OPT MATL, ROUND, 18"S/CD | 112.00 LF | $201.75 | $22,596.00 |
| Drainage Component Total | | | $162,651.00 |