FDOT Long Range Estimating System - Production R3: Project Details by Sequence Report
Project: 454217-1-52-01
Letting Date: 02/2029
Description: SR 5 (US 1) Resurfacing from SR 50 (Cheney Hwy) to SR 406 (Garden St), MP 0.000 to MP 4.117 & MP 35.686 to MP 35.699
District: 05 County: 70 BREVARD Market Area: 08 Units: English
Market Area: 08 Units: English
Contract Class: Lump Sum Project: N
Design/Build: N Project Length: 4.130 MI
Project Manager: HNTB/CB/RX
Version 7-P Project Grand Total $16,020,131.3 Description: SR 5 (US 1) from SR 50 (Cheney Hwy) to SR 406 (MP 0.000 to MP 4.117 & MP 35.686 to MP 35.699). (FY 28-32 Update 5/20/2026; Updated by KNHNTRX on 10/16/2025).
Resurfacing Lane Mile Cost $1,113,282.23
Project Sequences Subtotal $11,405,053.05
102-1 Maintenance of Traffic 10.00 % $1,140,505.30
101-1 Mobilization 10.00 % $1,254,555.84
Project Sequences Total $13,800,114.19
Project Unknowns 15.00 % $2,070,017.13
Justification for high %: Standard % for MOT/Mob. Recommend urban projects. 15% project unknowns for
Design/Build
0.00 % $0.00
0.00 % $0.00
Non-Bid Components:
Pay itemDescriptionQuantity UnitUnit PriceExtended Amount
999-25INITIAL CONTINGENCY AMOUNT (DO NOT BID)$150,000.00$150,000.00
Project Non-Bid Subtotal$150,000.00
Version 7-P Project Grand Total$16,020,131.32
Version 7-P Project Grand Total
$16,020,131.32