ROADWAY COMPONENT
| X-Items | ||||
| Pay item | Description | Quantity Unit | Unit Price Extended Amount | |
|---|---|---|---|---|
| 110-1-1 | CLEARING & GRUBBING | 0.32 AC | $22,500.00 | $7,200.00 |
| 515-2-311 | PED/BICYCLE RAILING, ALUM,42" TYPE 1 | 140.00 LF | $111.00 | $15,540.00 |
| 522-1 | CONCRETE SIDEWALK AND DRIVEWAYS, 4" | 1,565.00 SY | $86.00 | $134,590.00 |
| 522-2 | CONCRETE SIDEWALK AND DRIVEWAYS, 6" | 54.00 SY | $117.00 | $6,318.00 |
| Roadway Component Total | $163,648.00 | |||
SHOULDER COMPONENT
User Input Data
Description
Value
X-Items
| Pay item | Description | Quantity Unit | Unit Price Extended Amount | |
|---|---|---|---|---|
| 104-10-3 | SEDIMENT BARRIER Comment: Erosion control is included in main sequences 1-3 | 100.00 LF | $2.75 | $275.00 |
| 570-1-2 | PERFORMANCE TURF, SOD | 1,259.00 SY | $6.25 | $7,868.75 |
| Shoulder Component Total | $8,143.75 | |||
DRAINAGE COMPONENT
X-Items
| X-Items | ||||
| Pay item | Description | Quantity Unit | Unit Price Extended Amount | |
|---|---|---|---|---|
| 425-1-551 | INLETS, DT BOT, TYPE E, <10' | 5.00 EA | $8,500.00 | $42,500.00 |
| 425-1-910 | INLETS, CLOSED FLUME | 1.00 EA | $8,000.00 | $8,000.00 |
| 425-11 | MODIFY EXISTING DRAINAGE STRUCTURE | 1.00 EA | $4,420.00 | $4,420.00 |
| 430-175-118 | PIPE CULV, OPT MATL, ROUND, 18"S/CD | 336.00 LF | $201.75 | $67,788.00 |
| Drainage Component Total | $122,708.00 | |||
| Sequence 4 Total | $294,499.75 | |||