3

FUTURE PLANNING BOARD MEETINGS (CONTD.)

PLANNING BOARD MEETING MARCH 22, 2021

Block: 4201; Lot: 3 – Cedar Swamp Plaza, LLC

Block: 4201; Lot: 3 – Cedar Swamp Plaza, LLC Location: Cedar Swamp Road P/F Major Site Plan – to construct 5 self storage facility buildings and associated infrastructure. Applicant to correct the testimony of Traffic Engineer providing a Certified Traffic Expert on this application which was approved on 5/20/19 Engineer: Attorney: Decision Due Date: Hearing Status: Matrix Newworld Engineering Timothy B. Middleton, Esq. Time waived to 3/22/21 Initial Testimony

Block: 8601; Lot: 41 – 28 North Cooks Bridge Road, LLC

P/F Major Site Plan to construct11,305 SF two story professional office
Engineer:Haler Consulting
Attorney:Salvatore Alfieri, Esq.
Date Complete:11/5/20
Decision Due Date:Time waived to 3/22/21
Hearing Status:Initial Testimony

PLANNING BOARD MEETING APRIL 5, 2021

Block: 3601; Lots: 2, 3, 5 & 6 – Macedonia Baptist Church

Location: Cassville Road

P/F Major Site Plan with Minor Subdivision for Lot Consolidation
Engineer:Insite Engineering, LLC
Attorney:David J. Leone, Esq.
Date Complete:7/17/20
Decision Due Date:Time waived to 4/5/21
Hearing Status:Testimony given 1/25/21
Eligible: Dolan, Campbell, Riker, Jozwicki, Luisi, Brito, Wall, Flemming, Riccardi, Haring, Hudak

PLANNING BOARD MEETING APRIL 19, 2021

Block: 4201; Lots: 1 & 2 – Dreamview, LLC

Block. 4201; Lots: 1 & 2 - Dreamview, LLC
Location: 584 Cedar Swamp Road
P/F Major Subdivision and Major Site Plan
Engineer:Stonefield Engineering & Design, LLC
Attorney:Dennis Collins, Esq.
Date Complete:1/27/21
Decision Due Date:5/2/21
Hearing Status:Initial Testimony

Block: 4801; Lot: 24 – Ehrman Family Investment Co., LLC

Location: 440 N. County Line Road

P/F Major Site Plan – (7) contractor warehouses – 115,800 SF total warehouse area
Engineer:FWH Associates
Attorney:Salvatore Alfieri, Esq.
Date Complete:1/27/21
Decision Due Date:5/2/21
Hearing Status:Initial Testimony