3
FUTURE PLANNING BOARD MEETINGS (CONTD.)
PLANNING BOARD MEETING MARCH 22, 2021
Block: 4201; Lot: 3 – Cedar Swamp Plaza, LLC
Block: 4201; Lot: 3 – Cedar Swamp Plaza, LLC
Location: Cedar Swamp Road
P/F Major Site Plan – to construct 5 self storage facility buildings and associated infrastructure. Applicant to correct the testimony of Traffic Engineer providing a Certified Traffic Expert on this application which was approved on 5/20/19
Engineer:
Attorney:
Decision Due Date:
Hearing Status:
Matrix Newworld Engineering
Timothy B. Middleton, Esq.
Time waived to 3/22/21
Initial Testimony
Block: 8601; Lot: 41 – 28 North Cooks Bridge Road, LLC
| P/F Major Site Plan to construct | 11,305 SF two story professional office |
|---|
| Engineer: | Haler Consulting |
|---|
| Attorney: | Salvatore Alfieri, Esq. |
|---|
| Date Complete: | 11/5/20 |
|---|
| Decision Due Date: | Time waived to 3/22/21 |
|---|
| Hearing Status: | Initial Testimony |
|---|
PLANNING BOARD MEETING APRIL 5, 2021
Block: 3601; Lots: 2, 3, 5 & 6 – Macedonia Baptist Church
Location: Cassville Road
| P/F Major Site Plan with Minor Subdivision for Lot Consolidation |
| Engineer: | Insite Engineering, LLC |
|---|
| Attorney: | David J. Leone, Esq. |
|---|
| Date Complete: | 7/17/20 |
|---|
| Decision Due Date: | Time waived to 4/5/21 |
|---|
| Hearing Status: | Testimony given 1/25/21 |
|---|
| Eligible: Dolan, Campbell, Riker, Jozwicki, Luisi, Brito, Wall, Flemming, Riccardi, Haring, Hudak |
PLANNING BOARD MEETING APRIL 19, 2021
Block: 4201; Lots: 1 & 2 – Dreamview, LLC
| Block. 4201; Lots: 1 & 2 - Dreamview, LLC |
| Location: 584 Cedar Swamp Road |
| P/F Major Subdivision and Major Site Plan |
| Engineer: | Stonefield Engineering & Design, LLC |
|---|
| Attorney: | Dennis Collins, Esq. |
|---|
| Date Complete: | 1/27/21 |
|---|
| Decision Due Date: | 5/2/21 |
|---|
| Hearing Status: | Initial Testimony |
|---|
Block: 4801; Lot: 24 – Ehrman Family Investment Co., LLC
Location: 440 N. County Line Road
| P/F Major Site Plan – (7) contractor warehouses – 115,800 SF total warehouse area |
| Engineer: | FWH Associates |
|---|
| Attorney: | Salvatore Alfieri, Esq. |
|---|
| Date Complete: | 1/27/21 |
|---|
| Decision Due Date: | 5/2/21 |
|---|
| Hearing Status: | Initial Testimony |
|---|