PLANNING BOARD MEETING JUNE 21, 2021 (CONTD)
| Block: 3001; Lot: 1 – Adventure Crossing Phase 3 |
| Location: Monmouth Road |
| P/F Major Site Plan |
| Engineer: | Professional Design Services, LLC |
|---|
| Attorney: | Salvatore Alfieri, Esq. |
|---|
| Date Complete: | 5/6/21 |
|---|
| Decision Due Date: | 8/9/21 |
|---|
| Hearing Status: | Initial Testimony |
|---|
FUTURE PLANNING BOARD MEETINGS (CONTD)
PLANNING BOARD MEETING JULY 19, 2021
Block: 19501; Lot: 35 – Solomon Zolty Investments
Location: Grawntown Road
| Location: Grawlown Road |
| P/F Major Subdivision to include P/F S/P conditional use – Proposal to subdivide the existing lot into 21 SFD to include 4 |
| Affordable Housing & 1 Storm Water Lot |
| Engineer: | PDS |
|---|
| Attorney: | Adam Pfeffer, Esq. |
|---|
| Date Complete: | 12/4/20 |
|---|
| Decision Due Date: | Time waived to 7/31/21 |
|---|
| Hearing Status: | Testimony given 5/3/21 |
|---|
| Elicibility: | Dolee Gomboell, Bilar Jeyevicki Luici Well, Fleming, Hudak |
|---|
Eligible: Dolan, Campbell, Riker, Jozwicki, Luisi, Wall, Flemming, Hudak
Block: 8601; Lot: 41 – 28 North Cooks Bridge Road, LLC
| P/F Major Site Plan to construct | 11,305 SF two story professional office |
|---|
| Engineer: | Haler Consulting |
|---|
| Attorney: | Salvatore Alfieri, Esq. |
|---|
| Date Complete: | 11/5/20 |
|---|
| Decision Due Date: | Time waived to 7/19/21 |
|---|
| Hearing Status: | Testimony given 5/3/21 |
|---|
| Eligible: Dolan, Campbell, Riker, Jozwicki, Luisi, Wall, Flemming, Hud |
PLANNING BOARD MEETING AUGUST 2, 2021
Block: 12202; Lot: 1 – Jackson Baptist Church, Inc.
| Block: 12202; Lot: 1 – Jackson Baptist Church, Inc. |
| Location: 360 Bennetts Mills Road |
| P/F Major Site Plan |
| Engineer: | Lindstrom, Diessner & Carr, PC |
|---|
| Attorney: | Robert Shea, Esq. |
|---|
| Date Complete: | 3/26/21 |
|---|
| Decision Due Date: | Time waived to 8/2/21 |
|---|
| Hearing Status: | Initial Testimony |
|---|
Block: 22301; Lots: 5, 6 & 16 – Whitesville Business Park
Location: 370 Whitesville Road
| P/F Major Site Plan to construct (1) 14,940 SF warehouse building and (1) 78,300 warehouse building |
| Engineer: | PDS |
|---|
| Attorney: | Jan Wouters, Esq. |
|---|
| Date Complete: | 5/14/21 |
|---|
| Decision Due Date: | 8/17/21 |
|---|
| Hearing Status: | Initial Testimony |
|---|