All meetings shall be publicly noticed, recorded, and archived.
| Timeline | Deliverable |
|---|---|
| Within 60 Days | Completion of ordinance gap analysis |
| Within 120 Days | Release of initial public ordinance draft |
| Within 180 Days | Completion of public hearings and updated ordinance draft |
| Within 300 Days | Release of final ordinance draft |
| Prior to Expiration | Formal public hearing and Board consideration |
During the moratorium, neither Dubuque County nor any County department, board, commission, official, employee, or agent shall accept, process, review, approve, issue, or otherwise authorize any discretionary approval for a covered Data Center project or supporting infrastructure.
The Board of Supervisors shall hold weekly public work sessions throughout the moratorium focused on, but not limited to: