Page 10 of 39

for this or any other Fire District, the Township has reviewed the reversionary clause and hereby invokes the reversionary clause, causing the subject property to revert to the Township.

NOW, THEREFORE, BE IT RESOLVED by the Mayor and Township Council of the Township of Jackson, County of Ocean, State of New Jersey, as follows:

  1. That Fire District No. 4 failed to develop Block 2603, Lot 24 in a manner consistent with the terms of the Deed from the Township of Jackson dated April 17, 2002.
  2. That the Township does hereby invoke and enforce the reversionary clause as to Block 2603, Lot 24 (formerly Block 152.01, Lot 3.03) identified in that certain Deed dated April 17, 2002 between Jackson Township and the Jackson Township Fire District No. 4.
  3. That the Mayor is hereby authorized to execute any and all documents necessary to invoke the reversionary clause and any other document necessary and appropriate to carry out the actions herein.
  4. That this resolution shall become effective immediately.
  5. DATED: 12-18-2018
  6. ANN MARIE EDEN, R.M.C. TOWNSHIP CLERK
  7. RESOLUTION 373R-18
  8. TITLE: AUTHORIZE AS-BUILT/CLOSE-OUT CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE TOWNSHIP OF JACKSON AND SHORE TOP CONSTRUCTION FOR THE PROJECT KNOWN AS “CY 2018 PAVEMENT SPOT REPAIRS” WHEREBY DECREASING THE CONTRACT AMOUNT BY ($13,789.48 RESULTING IN AN ADJUSTED CONTRACT PRICE IN THE AMOUNT OF $193,182.53
  9. MOTION TO APPROVE BY: CALOGERO MOTION SECONDED BY: UPDEGRAVE YES: CALOGERO, UPDEGRAVE, NIXON, BRESSI ABSENT: MARTIN
  10. WHEREAS, the Township of Jackson previously awarded a contract to Shore Top Construction for the project known as “CY 2018 Pavement Spot Repairs” in the amount of $206,972.00; and
  11. WHEREAS, Township Engineer, Daniel Burke, has recommended the approval of As-Built/Close-Out Change Order No. 1 decreasing the contract by ($13,789.48) as a result of final as-built quantities (per attached “Schedule A”); and
  12. WHEREAS, the approval of this As-Built/Close-Out Change Order #1 will result in the return of the performance guarantee posted for this project. The return of said performance guarantee will be contingent upon the posting and acceptance of the required Maintenance Guarantee, which will run for a period of one (1) year.
  13. WHEREAS, it is now the desire of the Township Council to act upon the Engineer's recommendation and to approve said Close-Out Change Order No. 1.
  14. NOW, THEREFORE, BE IT RESOLVED by the Township Council of the Township of Jackson, County of Ocean and State of New Jersey, as follows:
  15. That the Township Council hereby formally approves and authorizes As-Built/Close-Out Change Order No. 1 to the contract between the Township of Jackson and Shore Top Construction decreasing the contract by ($13,789.48) for the project