Lee County Rest Area Feasibility Study Financial Project Indentification Number: 452377-1-22-01

LEGEND X = No ✓ = Yes

ALTERNATIVES EVALUATION MATRIX

ALTERNATIVE #

EVALUATION CRITERIA No Build Alternative # 1 Hybrid Flow Alternative # 2 Normal Flow Alternative # 3 Clockwise Flow

Description Traffic Pattern Counter-Clockwise Counter-Clockwise Counter-Clockwise Clockwise

Truck Parking Options Maintains the existing Facility as-is Provides both "Pull-Thru" and "Back-In" Provides both "Pull-Thru" and "Back-In" Provides both "Pull-Thru" and "Back-In"

Purpose & Need

Improves Safety Condition X ✓ ✓ ✓

Increases Truck Parking X ✓ ✓ ✓

Improves Modal Relationships X ✓ ✓ ✓

# of Parking Spaces

Truck 43 139 121 143

Personal Vehicle 75 51 51 48

Sociocultural Resources

Provides multimodal mobility and accessibility ✓ ✓ ✓ ✓

Archeological & Historic Sites X X X X

Utilities

Cost effective utility connections ✓ ✓ ✓ ✓

Drainage and Wetlands

Impacted Wetlands (acres) (includes secondary impacts) 0 6.2 6.6 6.4

Potential impacts to existing drainage infrastructure X Minor Minor Minor

Threatened & Endangered Species X X X X

Connection to Daniels Parkway sidewalks X ✓ ✓ ✓

Connection to existing Daniels Parkway bus stop X ✓ ✓ ✓

Enhanced Amenities

Expanded Rest Room Facilities X ✓ ✓ ✓

Right Of Way

Requires Additional Right of Way X X X X

Dog Walk / Park ✓ ✓ ✓ ✓

Picnic Shelters ✓ ✓ ✓ ✓

Children's Recreational Area X ✓ ✓ ✓

Walking Trail X ✓ ✓ ✓

Lake View areas ✓ ✓ ✓ ✓

Informational placards ✓ ✓ ✓ ✓

Truck Washing / Maintenance Area X ✓ ✓ ✓

Estimated Costs

Wetland Mitigation $0 $500,000 $500,000 $500,000

Right of Way $0 $0 $0 $0

Design $0 $3,500,000 $3,500,000 $3,500,000

Construction (includes cost of building) $0 $37,000,000 $37,000,000 $37,000,000

Construction Engineering & Inspection $0 $2,960,000 $2,960,000 $2,960,000

Preliminary Estimate of Total Project Costs $0 $43,960,000 $43,960,000 $43,960,000

Preliminary Analysis - Subject to Change