4. Designate the approximate dates on which the funding necessary to complete financing of those improvements will be deposited into the appropriate account or fund.
Those findings are to be made in conjunction with the annual reports discussed above. If such findings are not made as required by Section 66001, the local agency could be required to refund the moneys in the account or fund, per Section 66001 (d).
Once the agency determines that sufficient funds have been collected to complete financing on incomplete improvements for which impact fee revenue is to be used, it must, within 180 days of that determination, identify an approximate date by which construction of the public improvement will be commenced (Section 66001 (e)). If the agency fails to comply with that requirement, it must refund impact fee revenue in the account according to procedures specified in Section 66001 (d).