BUILDING FEES – RESIDENTIAL
In order to assist you in estimating the permit fees for your project, several tables and charts have been compiled and are included in this package. By following the steps listed below, a reasonable estimate may be made.
THE FOLLOWING BUILDING VALUATION DATA REPRESENTS AVERAGE COSTS FOR MOST BUILDINGS. THIS CHART IS ADJUSTED ANNUALLY AS RELEASED BY THE INTERNATIONAL CODE COUNCIL AND USED SOLELY FOR THE DETERMINATION OF PERMIT FEES.
STEP 1 – Find the type of project below and determine the value per square foot. Multiply this figure by the total square footage of the project. This will be the project valuation. Typical single family dwellings are Type 5B construction.
| Construction Group | Construction Type |
|---|
| 1A | 1B | 2A | 2B | 3A | 3B | 4 - HT | 5A | 5B |
|---|
| R-2 Residential, multi-family | $165.05 | $158.44 | $152.98 | $145.27 | $132.00 | $127.61 | $145.37 | $115.18 | $110.68 |
|---|
| R-3 Residential, one- and two-family | $154.04 | $149.85 | $145.98 | $142.32 | $137.11 | $133.50 | $139.93 | $128.29 | $120.75 |
|---|
| R-4 Residential, care/assist. living facility | $194.98 | $188.36 | $182.90 | $175.20 | $161.40 | $157.01 | $175.29 | $144.58 | $140.08 |
|---|
| U Garages | $83.66 | $79.00 | $74.06 | $70.37 | $63.47 | $59.32 | $67.24 | $50.19 | $47.80 |
|---|
| All Occupancies - Sprinklers | $2.40 | $2.40 | $2.40 | $2.40 | $2.40 | $2.40 | $2.40 | $2.40 | $2.40 |
|---|
| All Occupancies - Porch / Patio | $20.20 | $20.20 | $20.20 | $20.20 | $20.20 | $20.20 | $20.20 | $20.20 | $20.20 |
|---|
Development Impact Fees - $11,327.00 per single-family dwelling unit, and $7,639.00 per multi-family dwelling unit. This fee is used for parks, roads, and public safety capital improvement costs. Following is a break-down of these fees:
| Development Impact Fee Type | Single Family Cost per Dwelling Unit | Multi Family Cost per Dwelling Unit |
|---|
| Facilities | $1,334.35 | $716.95 |
|---|
| Fire | $328.81 | $232.13 |
|---|
| Parks | $5,045.87 | $3,847.12 |
|---|
| Police | $139.07 | $98.18 |
|---|
| Roads | $4,469.90 | $2,744.62 |
|---|
Victor Valley Water Reclamation Authority (VVWRA) or Industrial Waste Water Treatment Plant (IWWTP) Fees – VVWRA and IWWTP fees are used for the expansion of sewage treatment facilities, and can be computed by completing the form on page 4.
Sewer Capacity Fees – Fees are generally figured at a minimum of $350.00 per house connection.
Water Connection Fees – Please contact the Engineering Department for questions regarding costs.
Other Special Assessments – Depending on the location of the project, there may also be special assessment fees to cover storm drains, bridges, road widening, street lighting, and fire hydrant installation. Please contact the Development Department for more information regarding special assessment districts.
School District Fees – A Certificate of Compliance from the school district must be submitted to the Development Department.
Technology Fee – Multiply the Plan Review, Building Permit, Mechanical Permit, Electrical Permit, and Plumbing Permit fees by 4.8% (.048) to determine the Technology Fee.
Green Building Fee – Senate Bill 1473 which provides for the creation of the Building Standards Administration Special Revolving Fund.
| Permit Valuation | Fee |
|---|
| $1 – 25,000 | $1 |
| $25,001 – 50,000 | $2 |
| $50,001 – 75,000 | $3 |
| $75,001 – 100,000 | $4 |
| Every $25,000 or fraction thereof above $100,000 | Add $1 |
1