Prior Year Reported Public Improvements: The following are public improvements identified in the City's prior impact fee fund report: Annual Development Impact Fee Report – Fiscal Year Ended June 30, 2024 dated December 20, 2024. The table notes the estimated start date for each project, and whether construction began on the approximate date noted in the previous report. For any project identified for which construction did not commence by the approximate date provided in the previous report, the reason for the delay is noted as well as a revised approximate date that the City will commence construction.
Table 5: Prior Year Reported Public Improvements
| Fund | Fund Name | Proj. # | Project Name | Estimated Project Start | Project Phase | Reason for Delay | Revised Estimated Project Start |
|---|---|---|---|---|---|---|---|
| 354 | Parks | 81032 | Sports Complex Feasibility Study | FY 2022/23 | Not Started | At this time, the City is in the process of identifying the location for the Sports Complex. Once the location has been identified and the land has been acquired, the City will move forward with this project. | FY 2026/27 |
| 354 | Parks | 81004 | Eva Dell Dog Park | FY 2022/23 | Not Started | This is a component of a larger park project that has grant funding. The project has expenditures for the pre-construction phase that has been fully covered by the grant. The DIF funds will be utilized once construction begins. | FY 2026/27 |
| 354 | Parks | 81006 | New Rectangle Fields | FY 2022/23 | Not Started | At this time, the City is in the process of acquiring the site for the sports complex. Once site acquisition takes place, the City will move forward with this project. | FY 2026/27 |
| 354 | Parks | 81008 | New Walking Path | FY 2024/25 | Not Started | This is a component of a larger park project that has grant funding. The project has expenditures for the pre-construction phase that has been fully covered by the grant. The DIF funds will be utilized once construction begins. | FY 2026/27 |
| 354 | Parks | Trails Master Plan | FY 2025/26 | Not Started | The City has prioritized the development of smaller walking path projects at various parks throughout the City to achieve more immediate results. Once these smaller walking paths have been completed, the City will move forward with this project. | FY 2026/27 |