4. PUBLIC IMPROVEMENTS

This section of the Annual Report identifies each public improvement on which fees were expended and the amount of the expenditures on each improvement, including the percentage of the cost of the public improvement that was funded with fees.

FISCAL YEAR 2021/22 PUBLIC IMPROVEMENT EXPENDITURES

FundFund NameProject NameTotal Project FundingTotal Impact Fee Funded Amount% Impact Fee FundedTotal Prior Year Impact Fee ExpendituresFY 2022 Impact Fee ExpendituresImpact Fee Funding Remaining
352RoadNISQ/I15 INTERCHANGE-ST CONST$ 48,860,904$ 22,762,80347%$ 22,741,318$ 21,485$ 0
352Road352-60013 Green Tree Blvd Extension$ 80,550,764$ 19,005,39324%$ 692,143$ 9,218,145$ 9,095,105
352Road352-60014 Bear Valley Road Bridge over BNSF Railway$ 23,932,167$ 4,703,14020%$ 208,812$ 544,968$ 3,949,360
410Water410-74419 Project Area 31- Pipeline Replacement$ 1,550,000$ 699,84845%-$ 293$ 699,556
TOTAL$ 154,893,835$ 47,171,184$ 23,642,273$ 9,784,890$ 13,744,021

  • 352 Road NISQ/I15 INTERCHANGE-ST CONST 48,860,904 22,762,803 47 22,741,318 21,485
  • 352 Road 352 Road 352-60013 Green Tree Blvd Extension NISQ/I15 INTERCHANGE-ST CONST 80,550,764 $ 48,860,904 19,005,393 $ 22,762,803 24 47% 692,143 $ 22,741,318 9,218,145 $ 21,485 9,095,105 $

Expenditures Expenditures Remaining