SCHENKELSHULTZ SRQ Maintenance Hangar Add Service Fee Proposal #4 Construction Administration Services Hangar C, Airfield and Site Improvements REV 1 January 13, 2021 Page 3 of 4
accordance with the contract documents. Further, Architect will notify the Owner of any such act, omission, or failure on the part of the Contractor observed by A/E team during on-site visits
Architect will complete monthly site visits to check progress (total of 6 visits)
Civil Engineer will complete two monthly visits during construction (total of 12 visits)
Structural Engineer will complete one site visit to review foundation reinforcing prior to concrete pour
Mechanical Engineer will complete 2 site visits
Electrical Engineer will complete 2 site visits
Deliverables
Site visit reports will be prepared and distribute within 3 days of the site visit.
8.G Substantial Completion Punchlist
Level of Service:
Conduct one (1) site visit for substantial completion review by the A/E team. Prepare a punch list of items to be corrected prior to the final acceptance.
Deliverables:
Substantial Completion punchlist
8.H Final Completion Punch Walk
Level of Service:
Conduct one (1) site visit for final acceptance to review contractor's compliance and correction of the substantial completion punch list items.
Deliverables:
Final Completion confirmation documentation.
8.1 Project Close Out Record Documents
Level of Service:
Record drawings will be prepared incorporating construction changes and using information provided by the contractor via marked up field prints and field survey information. No field surveys are included in this task. Review of Contractor O&M manuals, warranty information and close out documents will be provided to ensure completeness and conformance to the specification documents.
Deliverables:
Electronic PDF and AutoCAD versions of the record drawings.
Specialty Services- Quality Assurance Testing and Quality Control Testing review
Level of Service:
1. Coordinate quality assurance testing for the sitework. AID and Terracon will prepare a civil and sitework scope of work for the QA testing in accordance with the project drawings and specifications.