FOURTH AMENDMENT TO THE DESIGN & BID PHASE SERVICES AGREEMENT BETWEEN THE SARASOTA MANATEE AIRPORT AUTHORITY Sarasota Bradenton International Airport AND SCHENKELSHULTZ ARCHITECTURE, INC.
Original Contract (dated September 25, 2019) $ 695,204.34
Amend No. 1, Revisions to 2nd Tenant Hangar from Elite Airways to Cirrus (March 27, 2020) $ 19,859.24
Amend No. 2, Revisions to Hangar C Size (June 1, 2020) $ 21,577.00
Amend No. 3, Delete MTC Program Scope from Bid Package (July 21, 2020) $ 13,085.00
Amend No. 4, Construction Phase Services (January, 2021) $ 107,978.58
TOTAL: $ 857,704.16